Questions tagged [tasks]

Questions relating to the management of individual tasks in a project or within project management software.

6 questions with no upvoted or accepted answers
Filter by
Sorted by
Tagged with
3
votes
1answer
2k views

How do you calculate the number of days between two tasks in Microsoft Project?

I've created an event planning project that explains all of the relevant tasks before, during, and after a given event in MS Project 2003. I would like to calculate the number of days between a given ...
3
votes
1answer
98 views

How can I show short tasks (less than 8 hours) in a JIRA Gantt chart?

I recently installed a few apps (like BigPicture) which help you see the order of work of each programmer. The problem is that when I link some tasks with estimates less than one work day, the Gantt ...
2
votes
0answers
47 views

Ms project - Avoid task split up in minutes

I am trying to update my ms project plan with the following: - replan al 0% and partly completed tasks from the new status date. - Tasks can be split up - Plan based on priority and available time for ...
0
votes
1answer
34 views

Microsoft Project 2019 - problem allocating resources to tasks outside their calendar working hours

We have a standard calendar work week. (Monday to Friday with weekends off) Our resources have "standard" calendar - so scheduling as standard for them is a normal work week. However, we have ...
0
votes
1answer
148 views

MS Project - how to set a task to finish before else start after a set period

I'm trying to set a task to either be wholly complete by 1st Dec, if not then start after 1st Jan (i.e. don't start at all if it can't be completed by 1st Dec). I don't want to split the task. Is ...
0
votes
1answer
3k views

Is it possible to show the percentage of completed task in the Timeline in MS Project?

I am using Microsoft Project 2013. I would like to visualize in the Timeline the percentage of completed task, for example 33%... Is this possible ?