Podcast #128: We chat with Kent C Dodds about why he loves React and discuss what life was like in the dark days before Git. Listen now.

Questions tagged [tasks]

Questions relating to the management of individual tasks in a project or within project management software.

5 questions with no upvoted or accepted answers
Filter by
Sorted by
Tagged with
3
votes
1answer
127 views

How can I show short tasks (less than 8 hours) in a JIRA Gantt chart?

I recently installed a few apps (like BigPicture) which help you see the order of work of each programmer. The problem is that when I link some tasks with estimates less than one work day, the Gantt ...
2
votes
0answers
57 views

Ms project - Avoid task split up in minutes

I am trying to update my ms project plan with the following: - replan al 0% and partly completed tasks from the new status date. - Tasks can be split up - Plan based on priority and available time for ...
0
votes
1answer
65 views

Microsoft Project 2019 - problem allocating resources to tasks outside their calendar working hours

We have a standard calendar work week. (Monday to Friday with weekends off) Our resources have "standard" calendar - so scheduling as standard for them is a normal work week. However, we have ...
0
votes
1answer
167 views

MS Project - how to set a task to finish before else start after a set period

I'm trying to set a task to either be wholly complete by 1st Dec, if not then start after 1st Jan (i.e. don't start at all if it can't be completed by 1st Dec). I don't want to split the task. Is ...
0
votes
1answer
3k views

Is it possible to show the percentage of completed task in the Timeline in MS Project?

I am using Microsoft Project 2013. I would like to visualize in the Timeline the percentage of completed task, for example 33%... Is this possible ?