All Questions
179
questions with no upvoted or accepted answers
4
votes
1
answer
430
views
Hiding a specific time period in Microsoft Project
Question
Good morning,
Is it possible on MS Project Pro 2019 to hide a period of time between two dates?
Background
Our construction projects are divided into 3 stages: (1) pre-construction, (2) ...
4
votes
1
answer
236
views
Determine to which task a resource is allocated on a particular day
Using a shared resource pool for several project plans (each plan is contained in a separate file), what is the simplest way of working out to which task a given resource is allocated on a particular ...
3
votes
3
answers
292
views
Is the Crystal methodology still practised anywhere?
The Crystal methodology is fairly often included in lists of Agile methodologies and it is easy to find articles from recent years giving an overview of it and comparing it to other Agile ...
3
votes
1
answer
193
views
Change task distribution with % completed
I'm using MS Project 2010. When assigning a task with duration say 5 days and work of say 10 hours. Then MSP distributes the occupation for that resource over the whole duration.
e.g.
Mon 2h | Tue ...
3
votes
0
answers
156
views
How can I create a task for two developers to support testing?
I'm trying to create a timeline for server migration. Typically when it comes to testing our developers spend about 25% of their time supporting the testing. (Running batch processes, answering ...
3
votes
2
answers
305
views
How can I show short tasks (less than 8 hours) in a JIRA Gantt chart?
I recently installed a few apps (like BigPicture) which help you see the order of work of each programmer. The problem is that when I link some tasks with estimates less than one work day, the Gantt ...
2
votes
0
answers
145
views
Auto-populate Lookup values from a custom field
I have written below code for custom field 'Product_task' to take values selected for field 'SFDC Product'
as options. However this doesn't seem to work always. Please let me know your suggestions.
...
2
votes
2
answers
97
views
How can I see 'next available' tasks in MS Project?
I'm used to creating project checklists in software such as OmniFocus, which shows me 'next available' tasks: those that are available now, aren't deferred, whose predecessors have been completed, etc....
2
votes
0
answers
197
views
Ms project - Avoid task split up in minutes
I am trying to update my ms project plan with the following:
- replan al 0% and partly completed tasks from the new status date.
- Tasks can be split up
- Plan based on priority and available time for ...
1
vote
2
answers
104
views
What is the term you use for a user that is a developer?
When developing a UI components software library, the "immediate" user of the library is not the end user interacting with the components on a website, but the developer who takes those ...
1
vote
0
answers
34
views
Ticket/task managment for multiple repositories on a same application
I'm looking for an improvement when managing work on one specific project.
Right now we have one application that has 3 repositories that are querying the same database. All three repositories (...
1
vote
1
answer
104
views
Is PRINCE2 truly in public domain?
I am a bit confused. I know PRINCE2 was released to be public domain in about 1990 but then I wonder why I cannot find any site (apart from prince2 wiki) with its content? Also, what is Axelos then an ...
1
vote
1
answer
69
views
Can I track tickets from one project in another?
I am the QA lead for a company that has multiple teams with their own projects in Jira. Is there a way I could track Jira tickets from for example, the engineering board or bug board in the QA board ...
1
vote
0
answers
23
views
Is it possible to restore a single project plan from a full database backup
Using MS Project 2013, one of our PCO deleted tasks from a project plan, while work had been entered via timesheets on those same tasks, some of which weren't approved, yet.
The project is now in a ...
1
vote
1
answer
72
views
Using Asana Boards in Kanban mode
Our (software development) team is using Asana and has broken down requirements, which were entered into the list view of Asana.
We have sections representing epics, and tasks below them representing ...
1
vote
0
answers
88
views
Automatically plan tasks as close as possible to deadline
I am hoping to use MS project to plan our manufacturing. I have added all of the units we need to manufacture for the coming year, as well as their deadline date (the date the units must be ready to ...
1
vote
2
answers
183
views
repeating processes and then making changes in MS projects
IN excell "=" duplicates the original cell ( does not copy once off) so if the original cell changes the duplicate cell also changes. How do I do the same when I repeat a process a multiple ...
1
vote
2
answers
52
views
MS Project Dynamic Portfolio Reporting
I have a team creating projects in MS Project. I need them to share their projects with me (in sharepoint?) so I can pull individual reports in real time. I then need to take those dynamic projects ...
1
vote
0
answers
355
views
What is the best practice for combining a pull request-based workflow with QA testing feedback in Azure DevOps?
Background
I am a developer in a large software development company. We have a git workflow where we have master which is our main branch, which is supposed to be stable. Everything that goes into it ...
1
vote
1
answer
178
views
MS Project chart for multiple projects
I am a project manager and I use MS Project to manage multiple projects. I use a shared resource pool. I have been playing with the charts feature, in the resource file to try to get a chart showing a ...
1
vote
0
answers
20
views
MS Project VBA_File subs not displaying
I have a number of modules written in MS Project that are part of a template for our project managers. Randomly, a user will indicate that the needed macros are not availabe. When I have them share ...
1
vote
0
answers
41
views
Ms project - removal of base calendar nonworking time not feeding through to resource calendars
I created recurring nonworking time on a base calendar. It correctly worked through onto the relevent resource calendars.
I added some nonworking time to individual resource calendars and all is still ...
1
vote
5
answers
251
views
Where does development process improvement fall into the product development lifecycle?
For most of my career as a software developer, I have been a part of Agile teams using Scrum, Lean Startup, or Kanban.
The Product team usually has goals for keeping the product running, improving the ...
1
vote
0
answers
48
views
MS Project cost
I'm facing a very weird behavior of MS Project when computing the project cost. Once removing subtasks from my original project I realized that changes to some subtasks are not reflected in the ...
1
vote
2
answers
165
views
portfolio optimization, with negative KPIs
In portfolio optimization, when having negative KPIs, what does it mean to select a subset of projects with contributions that result in a KPI end value to be less than 0?
For example, if we have ...
1
vote
0
answers
747
views
Fix for ProjectLibre incorrect critical path
I'm a big open source supporter, and want to switch from MS Project to ProjectLibre, however it does not display the critical path correctly for projects above a certain size. I'm wondering if anyone ...
1
vote
0
answers
258
views
In MS project, sub project tasks are not showing up in sprint task board
I added multiple sub projects to my current master project. I don't see the sub project tasks in sprint task board though I assigned sprints to tasks and "show on board" is yes. The tasks ...
1
vote
1
answer
919
views
MS-Projects -- Assigning a Resource group as resource
I am using MS Projects (desktop) and am wondering if it is possible to assign resources by the group they are designated under in the resource list. Essentially I would like to assign a team to a ...
1
vote
0
answers
194
views
Auto allocate resources
Is there any way to make MS project choose the resources for tasks between candidates that I've given to it? I mean there are several people who can do a task but how many of them and which ones are ...
1
vote
1
answer
136
views
Gantt chart with resource de-confliction
I like to use Gantt charts to model the time tasks will take and the dependencies of those tasks. For reference, I use GanttProject but I am not tied to it.
One issue I've had, however, is handling ...
1
vote
2
answers
330
views
Forward and Backward Pass Activity on Node Diagrams in MS Project 2010
I want to make Forward and Backward Slack Activity on Node Diagrams in MS Project 2010.
I display the Network Diagram view and choose Format > Box Styles. I Click the More
Templates button and in ...
1
vote
0
answers
57
views
How to cross project plan for enterprise resources, with leveling support in Microsoft Project Server
I'm using Microsoft Project Server on Sharepoint to manage project throughout the organization.
I have some enterprise (work) resources, that are simultaneously active on multiple projects.
The ...
1
vote
0
answers
89
views
MS Project. Need a field that flags what tasks have only completed predecessors that I can bring through to MS Project online
I'm using MS Project which is connected to a PWA. All users complete their tasks on the online 'Tasks' page. For the task owners, I need a flag that tells them that all the predecessors for their task ...
1
vote
0
answers
25
views
Resource Assignments
I have 4 Work resources entered into the Resource sheet and each has standard rates. I assign the work resources to tasks, but one of the tasks continues to display $0.00. Then when I double-click the ...
1
vote
0
answers
55
views
MS Project, Resource Availability, Task Usage work hours
I've been using other tools for awhile and have to jump back into MS Project.
I started a high level plan with tasks and resources, however, I'm having trouble remembering the specifics around Task ...
1
vote
0
answers
27
views
Approach for handling internal scheduling and global ticketing system in one JIRA instance
We have a following setup in my organization:
Company-wide JIRA instance (over 3000 users I think)
Organization JIRA instance (less than 200 hundred) with Tempo planner
The reason we have an ...
1
vote
0
answers
17
views
Enterprise custom fields are not rolling up in project center view
I am trying to sum project values by their project types. I created a project view then added some calculated enterprise custom fileds and ms project calculated fields like actual work and baseline ...
1
vote
0
answers
19
views
How to display individual resources with rolled up summary tasks?
I’m trying to see if there’s a view that can display each individual’s assigned task, with rolled-up summary tasks. Right now I have my project set up with summary tasks (milestones) and sub-tasks ...
1
vote
0
answers
24
views
MsProject - Updating board status based on %achieved
I would like to automatically update the 'board status' column based on the % achieved.
Is this possible?
1
vote
1
answer
129
views
Dynamically updating filters in a dashboard
The team I'm on has a couple of JIRA dashboards for our projects tracking tickets that were completed. Our process is to create a filter for that weeks completed issues, and then create a new ...
1
vote
0
answers
114
views
Auto Scheduling in Microsoft Project Planning 2016 is not working as expected
I scheduled many tasks in the AUTO schedule, However, it is not taking/changing the dates once I link all the tasks. Due to that, I selected the start date manually which is resulting in a different ...
1
vote
3
answers
681
views
MS Project Configuration - 80% allocation to project, max of 50% per task per day
I'm a newbie to MS Project here, so I was wondering if someone could point me in the right direction, or tell me if I'm barking up the wrong tree.
Is there a way to constrain a resource in MS Project ...
1
vote
0
answers
81
views
How to manage Cross-teams Roadmaps and high level tasks
Do you have any recommendations to track Roadmaps when working with multiple teams and cross-teams projects? Right now we work with Jira and spreadsheets, so any useful templates or tips for combining ...
1
vote
0
answers
210
views
how to create branch based project timelines
I am creating a forecast of a project timeline. In this I envision several swim lanes that will converge and fork as needed. sort of like product version controls.
Is there an easy way to generate ...
1
vote
0
answers
56
views
How to determine the human resources I need given financial and operational constraints?
I have a project and I want to minimize the costs. I am are responsible for the inspection of 1000 kilometers of sewer grid in Canada. My goal is to provide time high quality inspection reports. I ...
1
vote
0
answers
518
views
Confused by process of writing PERT chart
This is not a homework question but arises from self-study with full access to the answers. I'm not looking for the answers, but rather how to arrive at them.
I'm having trouble understanding how to ...
1
vote
0
answers
120
views
How to set dependencies in TeamWork app to cascade delays in one task into dates of other tasks?
Let's say I have multiple tasks that are supposed to be taken care of one after another. Each has its own date of completion.
task 1 - will be completed on 15 march (1 day)
task 2 - will be completed ...
1
vote
0
answers
26
views
How to update some Key information from another Project
I have created a Project in MS Project 2016. Of this data there are probably about 50 tasks which are of high importance.
What I would like to do is create a project with the most important 50 tasks, ...
1
vote
0
answers
1k
views
Project Online - Enterprise Custom Field Not Calculating Formula Correctly?
I am new to MS Project (~1 week experience) and could use some help with an Enterprise Custom Field I'm trying to create. I'm using Project through Project Web App in Office 365 (I assume this is ...
1
vote
0
answers
499
views
Asana and requirements management
I am looking for a way to include requirements management in Asana.
Right now we have a very powerful integration with Instagantt, where projects and their scheduled tasks are in sync with Asana's ...