All Questions

Filter by
Sorted by
Tagged with
24
votes
7answers
22k views

How do you schedule delivery dates in Scrum?

I've run into a constant issue. When a project starts, the client typically has a list of functionalities to be built in to the application. As a team we would like to follow Scrum. But the next thing ...
14
votes
4answers
20k views

What is the typical ratio of PM/EM hours to “work” hours in a project?

What is the rule-of-thumb ratio of Project Manager/Engagement Manager time to overall project time (e.g. man-hours for work products) in a project? I'm especially interested in an answer within the ...
149
votes
18answers
89k views

Why use story points instead of hours for estimating?

After using hours to estimate our projects for a long time and rarely coming within 20% of actual "work-to-ship," I have been told by a handful of people that "points" work a lot better at gauging the ...
71
votes
22answers
22k views

How technical should a Project Manager be?

Consider a software project involving a bunch of developers of mixed experience. The PM has the delivery responsibility for the project, but undertakes this through the team members. When the ...
11
votes
2answers
3k views

What are the definitions and distinctions between Project x Program x Portfolio x Product Managers?

What are the definitions, distinctions and relationship between the following roles? Project lead Project Coordinator Project Manager Program Manager Portfolio Manager Product Manager (optional) ...
18
votes
3answers
2k views

Handling bugs in the Scrum process?

I have recently gone live with a big project. To meet a tight deadline some technical debt was accumulated but the true extent only became apparent after go live. As this is intended to be a ...
5
votes
4answers
2k views

Defect Found in Previous Iteration - Bug or New Work?

A previous answer stated that: On the other hand, if Feature Bar met the Definition of Done in a previous iteration, but bugs were later found after the feature was declared "done," then while you ...
61
votes
5answers
6k views

Is Scrum a status report meeting or a developer meeting?

I'm a developer and we started using Agile last year (October 2011). And, it has been rough to say the least. I was always taught Scrum was to discuss the following: What you did yesterday What you ...
25
votes
7answers
5k views

Why use both story points and hours?

I'm a new scrum master for a team that is using story point estimation and hours. We do story points first during grooming and then hours during planning. I always thought of story points as being ...
22
votes
3answers
10k views

In Scrum, how to estimate research stories?

In our Scrum team, when there is uncertainty about a story or the team is not sure about how to implement it, we take up a research story first. Based on the findings of this research story, we are ...
16
votes
6answers
3k views

In scrum should incomplete stories be re-estimated or does the original estimate get burned down when it's finally completed?

If I have a story that's been estimated at 10 story points and we don't manage to complete it in a sprint how do you handle estimates for the sprint in which it's next included (assuming it gets ...
1
vote
5answers
4k views

Why must we define a Sprint Goal for each Sprint?

As a Scrum Team, we are committed to deliver Product Backlog items per the Product Owner's priority. The team doesn't understand why we should define Sprint Goals. How does that help?
40
votes
40answers
12k views

What is the Project Management book that left the most impact on you?

If you could recommend a single book that made you a better PM, which one would it be?
79
votes
11answers
24k views

Why can't the ScrumMaster and the project manager be the same person?

How a ScrumMaster does compare to a traditional project manager, and can either role coincide with the role of product manager or project sponsor / project owner?
32
votes
17answers
2k views

How to allow developers to get enough quality development time while keeping to support & maintenance obligations

I work for a small company of 6 multi-skilled developers where we have developed our own product which requires constant improvement but also maintenance and support, both for the current release from ...
9
votes
16answers
7k views

Project Management Software for a web development company [closed]

I have been doing freelancing with PHP, Ruby, and mostly open source frameworks for a long time. Now that I have a certain client base, they are giving me regular projects. I have decided to go in ...
10
votes
3answers
593 views

How should we plan work on support issues without a “battery”?

We are working on a very old project with a lot of legacy code. This means that we have around 3-5 unplanned issues every Sprint. We were handling that with "batteries": time set aside for ...
93
votes
9answers
38k views

How to estimate amount of work/man hours for an unfamiliar task?

Sooner or later we come across a task in our project, with which we are totally unfamiliar ('we' as in PM, but also possibly the staff assigned to do this particular task). How can we estimate ...
68
votes
7answers
116k views

What is the weighting difference between Epic/Story/Task

I am slightly confused between the three. From my understanding: Epic - Create a web site (T shirt size) (L) Story - Create the Home page (1 point) Task - Create a button on the home page that is ...
72
votes
14answers
92k views

When to Use Waterfall, When to Use Scrum ?

Where I lecture, I was always taught to use waterfall to manage projects, but when I finished college, waterfall wasn't the only method that can be used for project management, and I am very ...
62
votes
7answers
20k views

How to deal with unavoidable on-demand tasks in Scrum? Or should we even try?

I was put in charge of implementing Scrum in my Development Team. Unfortunately, the company I work with has a rather stale structure that does not go well with this framework. The team works on a ...
48
votes
4answers
15k views

What is kanban?

I'm curious as to what kanban is. I just learned about it seconds ago reviewing another question. (a) What is involved that would consider it Kanban? (b) Also how does it different from other ...
25
votes
7answers
4k views

Scrum, Agile, Kanban looking for 'for dummies' type of information [closed]

I'm sure I'm not alone in this. I have heard and read a lot of snippets of information about this topic and I've formed my own understanding - probably not the best way to assess the value or try to ...
30
votes
4answers
69k views

Which Scrum certification provider is most widely recognized or accepted?

I am planning to go for Scrum Master certification, and while researching the certification providers, I could not clearly make up my mind about which one was most widely accepted. There are two ...
22
votes
15answers
3k views

Which skill set is necessary for a project manager?

I know that this question depends a lot in the environment the Project Manager works in, but still want to know on the average, which skill/skill set that need to be focused more than others. To name ...
15
votes
4answers
3k views

Should velocity increase with time?

Some scrum masters are concerned with "bumping up" a team's velocity during a sprint, as if a higher velocity is better. But points are a relative measure of the work that a team needs to do for ...
25
votes
4answers
6k views

Why does Pivotal Tracker discourage estimating points for bugs and chores?

Pivotal Tracker "strongly discourages" estimating velocity points for bugs and chores – you have to change a setting and accept a warning to be able to do it. They explain why here, but I just don't ...
16
votes
4answers
30k views

Can I apply for PMP without experiences in all processes? What are the requirements for obtaining these certifications?

I am planning to apply for the PMP. However, all my project experiences were time related (event planning). I had no projects where I managed a budget. Would it be better to obtain the CAPM first, ...
8
votes
1answer
2k views

What are “Consumed Story Points” in Trello?

Some Scrum add-ons allow you to enter both estimated story points and consumed story points. What are consumed story points and how do you measure/estimate them?
4
votes
2answers
8k views

What to do when mid-sprint, you realize some stories won't be done?

On the seventh day of a two weeks Sprint, we realize that 20 percent of the stories cannot be completed. What is the best action to take? Is it possible/recommended to cancel the iteration on start ...
6
votes
2answers
882 views

How to differentiate old bugs from new bugs during a sprint?

In a sprint where we fix old bugs as well build new features, we will encounter 3 types of "bugs" in in a scrum board: Bugs introduced by current stories Bugs newly discovered during sprint but are ...
111
votes
14answers
13k views

How to Avoid Micro-Managing a Software Development Team? [closed]

I've managed a few projects over the last few years, and one of the biggest challenges I face is avoiding becoming a micro-manager. I worked with a team once where I worked with a group of software ...
50
votes
25answers
28k views

How do I measure employee (software developer) performance based on bugs created?

I am trying to implement KPI for employees of my company. One of the KPI have listed is the quality of code, as measured by bugs created by developers. Now my problem is: I am planning to give 40 ...
29
votes
9answers
925 views

Should a PM also be a resource on the project? Why?

we have a small team of highly technical people and one of them is the project manager for the project. The person who is in PM role for this project is experienced and has previous project management ...
18
votes
9answers
124k views

What are the differences between project leader and project manager

Is there any difference between a project leader and a project manager? Is their involvement different in any aspect? What are the tasks performed by project managers? What are the tasks performed ...
25
votes
7answers
4k views

Is PMP certification an appropriate career goal for someone about to start a career in project management?

Is PMP certification a requirement for a successful career in Project Management? At which point would it be appropriate for a newly starting project manager to plan to include PMP certification?
35
votes
8answers
3k views

Strict or pragmatic Scrum?

Do you practice Scrum strictly after its rules or are you going a more pragmatic way, picking out the bits that suit you/your environment best, maybe mixing it up with other methodologies ? In other ...
15
votes
10answers
3k views

What time tracking / time management software do you use? [closed]

I made a few searches for such a question and I did not discover any. So... have you tried implementing and actively using a software that is tracking employees time spent on different assignments? ...
10
votes
3answers
14k views

Can we add more user stories to the Sprint Backlog if the requirements change during a sprint?

We are currently working on a project where we receive a lot of change requests, and the client insists that we should deliver the changes in the current sprint! Can I add the new work to the sprint ...
20
votes
6answers
3k views

What role is there for a PM on an Agile project?

Back before agile was everywhere, having a PM on all but the smaller projects was considered essential. Now, only the largest projects have people assigned to just in a PM capacity. I guess I have ...
3
votes
4answers
4k views

Agile “user story” for a user-less project

Disclaimer: I'm a total agile newbee. As a project manager for a pilot agile project, I am trying to create a rough sketch of my project using agile methodologies, but somehow I am not sure how to do ...
13
votes
5answers
449 views

Discerning estimate validity

I've had experiences in the past where different developers will give different qualities of estimates--which then have to be consolidated into a single project plan--only with a twist. One ...
8
votes
7answers
2k views

Sprint Goal and Failure of a Sprint

My organisation is pushing for strictness on what they consider a Sprint Failure or not. They have decided that if there are any User Stories not fully completed (as per the DoD) at the end of the ...
4
votes
3answers
769 views

How to handle tasks from previous Sprint on current Sprint Burn down chart

Let's say a project has 2 or more Sprints and for each sprint you are using a burn down chart to track the Sprint progress. If at the end of the first Sprint there are tasks that have been started but ...
7
votes
3answers
1k views

What are the right conclusions to draw from the success or failure of a Sprint?

I recently encountered the opinion that, if a Sprint is successful due to statistical reasons (e.g. the team made big mistakes during planning but the team delivered its stories anyway), then that's ...
5
votes
3answers
399 views

How do we deal with bugs in scrum environment

We recently began working on Scrum with one of our products. Prior to that we worked with a Waterfall methodology. We have created stories for the new feature and also included the bugs for the next ...
4
votes
4answers
4k views

Is there are a resource handler or gantt chart creator tool for JIRA? [closed]

I'm hoping someone has some experience on tools and/or better keywords to describe this problem: I have JIRA system for developers where they provide estimates and track time completed. The estimate ...
66
votes
10answers
4k views

Minimum Project Management Practices for One-Man Software Projects

I've worked a lot on projects by myself -- "one man" projects. These are typically small projects in the software domain. Many of them have no customers other than myself (who actually use the end ...
89
votes
9answers
83k views

Why would teams use the Fibonacci sequence for story points?

Why do some teams use numbers from the Fibonacci sequence as story points? Is it just a preference, or is there something more to it?
21
votes
6answers
113k views

PMP Experience Documentation [closed]

I am looking to take the PMP exam in a year or so, and see that one of the requirements is "at least three years of project management experience, with 4,500 hours leading and directing projects." ...

15 30 50 per page