All Questions

Filter by
Sorted by
Tagged with
0
votes
0answers
5 views

Where can I download a real WBS for a large complex engineering project?

eg. do NASA publicly release WBSs for any of their projects? I would like lots of detail, so I can show my team what to aspire to. Most of the WBSs that I've seen online are not very detailed, they ...
0
votes
1answer
12 views

Sprint Planning for Agencies

I'm looking for some help finding resources on sprint planning specifically for agencies. Resources seem plentiful for in-house software teams, but not so much for agencies. Specifically, planning ...
0
votes
0answers
16 views

Time managment tool

I'm looking for a tool that can help organize my wife's work. She gets assignments with due dates. The perfect tool would allow to insert the task, due date and estimated work time needed. Them, it ...
0
votes
0answers
38 views

How large IT companies like google separate responsibility between departments? [closed]

How large IT companies like google separated responsibility between departments? How they separated tasks, roles? What is their organization chart? I want a documentation about processes for develop ...
2
votes
3answers
131 views

Does such physical-whiteboard-per-team management process exist in the literature?

Does the following sound similar to some established (now or in the past) practice? One big whiteboard per team. Tasks are written down in a single short sentence(e.g. "refactor Frubnicator" ...
0
votes
0answers
30 views

Jira Structure Resource Leveling uses random order

I am using Jira Structure with Gantt and trying to schedule tickets on the project with resource levelling. Instead of levelling one-by-one, it places first a ticket from the end of a structure, then ...
-1
votes
1answer
66 views

Using Gitlab for specifications

We are already using Gitlab in our development process. We want to integrate our specification files (which currently are Word documents) into our repository, in order to leverage the versioning of ...
0
votes
1answer
43 views

Using EVM would purchase orders be actual costs or estimates to complete?

I am getting my head wrapped around EVM. How should one account for items like purchase orders? In my experience until invoiced POs are treated by accountants like it doesn't exist until you get an ...
0
votes
2answers
62 views

Variable Duration to Show Increased Speed (MS Project)

In MS Project, is there a way to show the improvement in duration of a repeated task using a variable duration? The project I am working on has multiple tasks that happen over and over again. Over ...
1
vote
6answers
157 views

User stories when starting from scratch

A user story is defined in quite a few ways, but roughly always like this: User Story is a small (actually, the smallest) piece of work that represents some value to an end user and can be delivered ...
5
votes
5answers
890 views

Adding user stories to nearly complete features?

I am a new PM. My company uses Rally for project management. I'm not too sure if this is a standard across platforms, but in Rally you can assign user stories to a parent feature. My team has been ...
1
vote
0answers
64 views

Fix for ProjectLibre incorrect critical path

I'm a big open source supporter, and want to switch from MS Project to ProjectLibre, however it does not display the critical path correctly for projects above a certain size. I'm wondering if anyone ...
4
votes
4answers
135 views

Is onboarding a non-functional requirement?

I work on a team that manages DevOps tools for a software company. When an engineer from one of our product teams wants to use one of our tools, they clone a series of Jira tickets and work through ...
1
vote
0answers
57 views

In MS project, sub project tasks are not showing up in sprint task board

I added multiple sub projects to my current master project. I don't see the sub project tasks in sprint task board though I assigned sprints to tasks and "show on board" is yes. The tasks ...
0
votes
2answers
110 views

Issue Register for day to day work?

I've seen the concept of an Issue Register in PRINCE2 but that would for issues and risks during a project that well end as they all should do. I've never used one in practice for either a temporary ...
0
votes
1answer
75 views

Creating a PaaS using scrum

If one were to build say a Windows Azure "clone", what would be considered an increment that is "potentially releasable"? e.g. Releasable vs shippable? I can not envision what ...
1
vote
4answers
118 views

Backlog - Is this to (i) List outstanding 'user stories' or (ii) List outstanding 'tasks' or (iii) Can one be used for both purposes?

Any good links to example backlogs would be appreciated. I understand from a backlog user stories can be refined, added, removed and so on. I'd imagine tasks or a WBS would be constant or tweaked by ...
0
votes
3answers
98 views

Backlog grooming items planning

In a Scrum project if the team is from 4 developers, the sprint is two weeks long, Team Velocity is 40 SP/Sprint and the Focus Factor is 0.6. During the Backlog Grooming meeting, user stories with how ...
4
votes
4answers
256 views

What is a good example of a project to use to demonstrate how to build a Microsoft Project Schedule

I want to train a few new team members in the use of Microsoft Project. All are familiar with the basics but I want to explain WBS hierarchy and predecessors. I am trying to think of an 'every day ...
0
votes
1answer
72 views

Minimalistic, free project management site with tree-like task structure?

I'm looking for a project management site, that has a free version, that can be accessed by multiple people enables entering tasks for which you can add any number of fields with values (like "...
1
vote
3answers
119 views

If a team works on different things, how can they run sprint planning effectively?

I'm a Scrum Master for a team who are working on different features for different products, but all for the same company. As we're a small team, we've kept it to 1 team and have been sprint planning ...
0
votes
2answers
68 views

Using project management tools like MS Project or Primavera in an agile team

Do project management tools like MS Project and Primavera make sense in a software team and for a software product, assuming that the team is following agile practices and uses, e.g., Scrum. Are ...
0
votes
0answers
67 views

How do I calculate a % complete on tasks which are due before a certain date with rollup function in MS Project

For a project that I am managing in MS Project I would like to have a % complete of tasks that need to be finished before Q2. E.g. I have one task with 10 sub tasks. 5 of these sub tasks have a due ...
0
votes
0answers
65 views

Customize the TFS Scrum board

Here is a TFS Scrum board I got from Internet: I want to know if it is possible to customize the card, as it does have the name of attributed person as redundant information. I would want to replace ...
12
votes
10answers
2k views

should developers have a say in functional requirements

In general most online resources point out that the functional requirements are the responsibility of the business analyst or product manager. But developers sometimes can be the expert on a product e....
7
votes
6answers
1k views

ex-Development manager as a Product Owner

In a new team, an ex-development manager, who's been in that position for many years, opted in as the team's Product Owner. The team has decided to do Scrum. The PO's Agile mentality is certainly ...
0
votes
0answers
100 views

Too much to test on the last day of the sprint [duplicate]

How can I avoid the issue where a lot of stories are moved to Under Testing on the last day of the sprint? The Under Testing column is manageable on most days but on the last day and there day before ...
0
votes
1answer
74 views

Project Management: Resource Availability

I have a meeting that needs to be attended by 10 individuals. Each of these individuals is either a manager, director, or member of executive leadership. There is very little overlapping availability, ...
0
votes
1answer
64 views

Is Dividing By a Percentage Valid in the Context of Determining Cost per Acquisition/Return on Investment?

I'm currently trying to find the return on investment (ROI) for a specific campaign, and I can't figure out if the formula below is valid in the context it's being applied; please see the first part ...
2
votes
4answers
175 views

Cadence in Scrum

Scrum coaches say that a Scrum Team (often Scrum Developent Team is meant) should adhere to: predictable cadence delivering business value each Sprint But at the same time Scrum emphasizes that ...
1
vote
1answer
49 views

How can I show the month for a Enterprise Custom Date Field in the Project Center for Grouping?

I setup a Enterprise Custom Field for a Key Date that leadership wants to group by year and month. I thought I could just make 2 new Enterprise Custom Fields, one to parse out the Month and the other ...
0
votes
1answer
59 views

Do I have EVM Planned Value understood correctly?

I am struggling to get all the PMI EVM terminology sorted out. The last key for me was planned value (PV). Let say I have a task and my BAC is $100,000 and scheduled for 4 weeks. 2 weeks in I am done ...
1
vote
5answers
142 views

Who should train business stakeholders on Project Management basics?

To clarify, I'm working as a Project Manager for a company where such concept was mostly unknown across business stakeholders. While projects were being done, no specific project management framework ...
2
votes
3answers
95 views

Can a story be re-open within sprint in Agile?

Here is the scenario. Story was completed as written and scheduled for the next release. We found out a day later that there were other systems that needed to do changes as well and would not be ...
1
vote
1answer
48 views

MS-Projects — Assigning a Resource group as resource

I am using MS Projects (desktop) and am wondering if it is possible to assign resources by the group they are designated under in the resource list. Essentially I would like to assign a team to a ...
0
votes
1answer
94 views

Team managemnet to get something streamlined

I am unofficially given an opportunity to lead a very strong technical team. We work in 24*7 Shifts there we have shift handover happening 2wice a day. Currently we are just preparing a set of table ...
0
votes
2answers
72 views

Best way to manage programs?

My company is starting a new program that will consist of many projects: An Android application An iOS application A web application A backend to support the applications A business analysis A brand ...
7
votes
8answers
3k views

From a sprint planning perspective, is it wrong to build an entire user interface before the API?

I'm currently reading 'Agile Estimating and Planning' by Mike Cohn and it mentions to not split by tasks like 'build user interface' and 'build middle tier', and instead to focus on building something ...
1
vote
1answer
47 views

Planned / earned value for items outside of the project scope?

Getting my head wrapped around the PMP / PMI earned value methodology. Traditionally have tracked a project budget vs the actual spend on a simple basis with that being the variance etc. The scenario ...
1
vote
1answer
36 views

Is it possible to display multiple tasks on a single line using ProjectLibre?

I have a project that I have 15 main tasks on. One of them is Meetings. I have had X meetings, and the duration is 1-day. Is there any way to show multiple bars on a single line showing these Meetings ...
0
votes
1answer
69 views

Giving credit via Scrum or Kanban boards to developers participating in release-management and validation activities

I have a team of developers participating in two week Scrum sprints. We track our sprint progress (code pushes to QA region, bug-fixes, prod-support) in Jira. The team also participates in monthly ...
1
vote
2answers
53 views

Using Kanban with Optional Columns

We have an optional column for Review, only 20% of tickets need reviews and most don't. Here are our columns: Todo/Backlog Development Reviewing Testing Done How do I implement optional columns in ...
2
votes
2answers
45 views

Microsoft Project - manage project with tasks that can be completed in any order

0 Probably best described by example: I have a project with 10 tasks of 1 day to be done by 1 resource. So they have to happen sequentially, easy to arrange by levelling or linking and the project ...
1
vote
3answers
81 views

How to build a feature backlog bottom up

Does anyone have any experience with bottom up product management? Essentially getting their teams to decide on the features and the direction of product? In most of my previous teams - product ...
0
votes
4answers
97 views

Can each Product have its own P&L?

It's often said that a Product Owner is a mini-CEO. Let's say we are talking about a company that is developing a large, complex product. In this case there're usually more that one Product Owner, ...
1
vote
2answers
77 views

How to decide what is a problem and what not in Product Management?

I understand that these problems can emerge in a variety of situations: There is a specific goal set by management, then the current situation has to be evaluated and decide what needs to be changed ...
1
vote
4answers
119 views

How to handle a Sprint completed ahead of time? [duplicate]

Let's say we have a sprint of 2 weeks. In that sprint, the IT team has to implement some issues or features. How can we handle the case where the team finishes all issues/features ahead of time? Do we ...
1
vote
1answer
47 views

What type of production/project framework is use with products with long lead times and high upfront costs, such as automobiles

I am aware that million dollar presses are used in stamping out auto parts. I am aware that million dollar robots are utilized in assembly of autos. I am interested in what production/project ...
0
votes
0answers
36 views

How do you close out a Scrum Sprint in Azure Boards? Especially, what should you do with partially completed user stories and tasks?

I am new to Azure Boards and finding it can be very confusing when it comes to scrum sprint ends and planning the next sprint. What should you do with user stories and their tasks that are only ...
0
votes
1answer
63 views

MS Project - Task constraints based on dates of other tasks

I would like to be able to set task constraints based on dates relative to other tasks, for instance: "taskA to start no earlier than taskB end date + 20 days" is there a way to do it? In MS ...

15 30 50 per page
1
2 3 4 5
116