MS-Project 2010: Task end-date seems to be calcuated incorrectly

I am using MS-Project 2010 and have noticed something peculiar in how "end-date" of the task is dislayed. I obeserve the following behavior: 1. I set the task to start on Monday. 2. I set the duration for 5 days. Strictly speaking my task should finish at the end of the working day on Friday, yet MS Project shows the completion date as the following Monday. Linking next task to this one, sets the start date correctly to the following Monday.

Any advise, on how to interpret this behavior and whether it is possible to show the completion of the task as Friday in my example?

Thanks, Denis