You can use standard FS relations for predecessors, and set task constraint type 'As late as possible':

    1 milestone - prerequisites: 2,3
    2 Activity A - 4
    3 Activity B - 4
    4 Activity C

You should set 'as late as possible' constraint on tasks 2-4, and set task 1 to the required fixed date ('start no earlier than' constraint).