A POC can not be estimated in terms of story points, hours, or any sizing you use, since it is all about trying to prove if a suggested model works or not. That's why, it can not be included in a sprint.

As far as I understand, the need to include it in the sprints arises since;

 1. some of the resources in the scrum team will be working on that POC
2. the output of the POC will be epics, stories, tasks for the scrum team

You should approach this POC just like how you approach to a bug from the production environment; have a kanban board for these kind of activities and add the POC there. In terms of the workload of the scrum team members, you can use the same model you use when a member uses a paid time off ( vacation ).

I would recommend the PO to do the communication between the external and internal teams because the POC is mainly done for the PO; the outputs of it will define what needs to be done. While the POs do the communication, they can do the planning to act faster.