For example: in Sprint 2, on story, A Tester raises 4 bugs. 2 bugs got fixed in the same Sprint. The remaining 2 were pushed to the Product Backlog. At Sprint 6, we are picking those 2 bugs of story A to fix. Do these 2 bugs need to be estimated for Sprint 6?