5
votes
Accepted
Critical Path in agile project
First off, if I can recommend, call them interations. Sprint is a specific branded name for a Scrum iteration. Iteration is a more generic term used in agile and other lifecycles. You're doing your ...
3
votes
Accepted
How do I identify critical path in MS Project?
Standard Answer:
1. Check the "Critical Tasks" box in the Bar Styles group of the Format ribbon. That will enable the red bars on the bar chart.
OR
2. Apply the built-in "Critical" filter in the Data ...
3
votes
How can my PERT diagram take account of my resources?
This video shows how to organize the problem with a table, and proposes a simple greedy slack based heuristic solution: https://www.youtube.com/watch?v=7AJ73qxZtsI
This page http://www....
3
votes
critical chain project management
If we go back to PMBoK basics, the definition in the 5th edition is is:
Critical Chain Method: A schedule method that allows the project team
to place buffers on any project schedule path to ...
3
votes
Accepted
Critical Path Method (CPM) algorithm
On the backward pass the latest possible completion time of job 5 is 26
You can see another example on the PMI site - Understanding the basics of CPM calculations
Forward pass: For the earliest ...
2
votes
time management
if the distribution of duration values is symmetrical (+- sigma), then the expected value will be the actual estimate without this variance, so you can use it simply for critical path estimation.
if ...
2
votes
How to show secondary and tertiary critical path in MS Project?
Sure there is. Temporarily apply a deadline date to the Project Complete milestone. Choose a date that is drastically far behind (maybe a year behind) the milestone's current finish date. This ...
2
votes
What is the "critical path" when drawing an activity-on-node network diagram that doesn't converge?
Project Management Answer
Analysis
The critical path is, by definition, the longest path between two nodes. Wikipedia says (emphasis and italics mine):
CPM calculates the longest path of planned ...
2
votes
Why in PERT the activities duration follows a Beta distribution
This is interesting. If you follow best practices for defining distinct activities to be estimated and tracked, then I think they really do meet these conditions.
every event is independent by the ...
2
votes
How to solve the project network diagram
Why Test Questions and Homework Questions Like This Are Bad
In general, the only "correct" answer is the one that your teacher (or the test designer) says is correct. Your question is a great example ...
2
votes
Critical Path in agile project
Try to plan a few iterations up front, so you can reduce delays that are caused by not finding out / addressing points in time. As a general rule,
You must see all the tasks that will be necessary ...
2
votes
Activity on Arrow diagram: simplification allowed when sequence is predecessor of next node
I'm going to go the other route from the existing Answer and ask:
What useful information does the first diagram have that the second does not?
Going by the law of transitivity, if C implies D and D ...
2
votes
Accepted
Start and End node in Critical Path Calculation
Yes, adding start and finish milestones to the network is correct. (Calling them "dummy nodes" is unconventional, as that term is usually reserved for activity-on-arrow diagrams.)
You might want to ...
2
votes
Are all nodes in Activity-on-Arrow diagrams milestones?
TL;DR
What if I need to show several activities like a1, a2 and at the end of a2 there is a milestone?
In activity-on-node (AoN), you'd be looking for the concept of "virtual nodes." Standard ...
2
votes
Are all nodes in Activity-on-Arrow diagrams milestones?
In an Activity-on-Arrow diagram, all of the nodes represent a specific achievement in a project with zero duration. A milestone is also an achievement in a project that doesn't impact duration.
It's ...
1
vote
Project crashing
There's a great article on project crashing in PMI that addresses your concerns.
...
In practice the most common requirement for project re-planning
calculations concern time and cost. ...
1
vote
Accepted
What's the term for duration minus drag in CPA?
A.L. Steve Devaux here. It's an interesting question that I've never thought about! Tom Boyle (who pointed me here) suggests “critical concurrent duration”, which is pretty good. I think "multipath ...
1
vote
How do I identify critical path in MS Project?
The red line in the Gantt chart usually identifies the critical path.
1
vote
Activity on Arrow diagram: simplification allowed when sequence is predecessor of next node
First I'd adjust the length of the arrows to the length of the task. At least that's the way I'm using it.
Ad your question: You are not required to use dummy activities. But I'd chose to do so. ...
1
vote
How to show critical path INCLUDING completed tasks (in MS Project 2010)
You are describing something like an as-built critical path, which is not easily created even in the best of circumstances.
MSP sets the Critical flag based on total slack, but total slack becomes ...
1
vote
Accepted
Why in PERT the activities duration follows a Beta distribution
Estimation, like a lot of things in the PM world is both an art and a science. PERT is a good rule of thumb, but it is just a place to start.
For some projects I've seen estimates use (opt. time + ...
1
vote
What are the known problems with the Critical Path Method?
If you do not know or understand your critical path in your schedule, then you are not managing your schedule. I have not seen anything else take its place so, as far as I know, CPM is still a ...
1
vote
Accepted
How can my PERT diagram take account of my resources?
The CPM schedule as defined is not achievable due to resource
over-allocation. A "critical path" definition for an unrealistic schedule is fiction.
Assuming you are using one of the conventional ...
1
vote
WBS and PERT diagram
Your network diagram should show all leaf level WBS elements in the sequence as indicated in your work logic. So milestones would be included. You may not show the phase necessarily but if you ...
1
vote
Accepted
WBS and PERT diagram
Early versions of PERT diagrams had "PERT Events" that were all milestones or gates with task information embedded in the arrows. This has changed over the years but most PERT charts I have seen "in ...
1
vote
Critical Path Analysis
While recognising that this is an exam question, this type of situation is common in many projects, especially where dependencies are identified and entered into the plan at different stages in the ...
1
vote
Critical Path Analysis
If it is an exam question, then it stands to reason that it is intentionally confusing. Simplifications such as applying the Law of Transitivity are intentionally avoided.
That being said, it is not ...
1
vote
Two activities generate two activities? (Network diagram)
Try to give it a real life situation and it will make sense to you. When you make dinner, it's ready at 7:00. One person may use your output at 7:10, and another person at 7:30, the second person ...
1
vote
Earned Schedule results versus Critical Path and Finish Variance results
Generally speaking, I've found more complex models to be more difficult to "get right". Unless you are willing to spend the time to customize a complex model, the fact that more variables are being ...
1
vote
Items which feed critical path activities
Few thoughts:
If Activity A is part of the project plan, it can be also on the critical path. Please refer your network diagram and also check what is the dependency between Activity A & B. Is it ...
Only top scored, non community-wiki answers of a minimum length are eligible
Related Tags
critical-path × 32ms-project × 3
scheduling × 3
dependencies × 3
planning × 2
schedule-risk × 2
critical-chain × 2
agile × 1
team-management × 1
estimation × 1
sprint × 1
project-team × 1
pm-software × 1
process × 1
methodology × 1
ms-project-2010 × 1
gantt × 1
waterfall × 1
resources × 1
work-breakdown-structure × 1
bugs × 1
constraints × 1
projectlibre × 1