16
You have three factors:
Money
Time
Requirements
If money and time are fixed and requirements can change then you would go after SCRUM.
If requirements are fixed then you would go after waterfall.
13
I won't say that it is all about communication, but I think a large portion of the problem you see can be contributed to communications that could be improved.
I work in the same field, and I've seen this behavior from many clients in different industries. What took me a long time to understand was that the way I initially present estimates can have a huge ...
12
checking SVN in a daily basis to review codes and to assess how much codes have been committed by each developer is a good way. is it fair and used in industry?
The proposed metric is utterly unfair, regrettably is used in some organisations and is in my personal opinion a recipe for disaster.
HasaniK and Jakub have already identified some very valid ...
11
First, remember that an estimate is highly unlikely to be 100% correct, so do the best you can with the information that is available to you.
Second, break down the tasks as far as you reasonably can, and get figures for similar low level tasks from other projects that have been done in the past. Don't worry if they are not identical, as long as they are ...
11
You shouldn't be allocating story points to cards. The team should estimate the cards and agree on what to pull from the backlog based on their velocity.
The team is accountable for making their own forecasts and sprint plans. You telling them what must get done in the next week is neither Agile nor Scrum. You're also likely demotivating your team ...
9
Have you considered a Squad system? The always-excellent Henrik Kniberg has an article that you may find useful on how this system is used at Spotify.
The basic principle is as follows:
Vertical multi-skilled (product, development, design) teams work on a single product or area of product development (e.g. infrastructure, customer feedback) - these are ...
9
checking SVN in a daily basis to review codes and to asses how much codes have been committed by each developer is a good way. is it fair and used in industry ?
This is definitely not a correct measurement for a PAR for Software Engineers. As Jakub has also mentioned, design takes time,sometimes there are blockers which prevent dev team from finishing a ...
9
The biggest problem is Brooks' Law
You did not say why you are trying to add freelance developers to the small project temporarily. If your project is late and you are hoping to crash the time line, remember Brooks' Law, "adding manpower to a late software project makes it later".
It takes some "ramp up" time for the resources added to the project to ...
answered Jul 17 '15 at 13:12
Ashok Ramachandran
9,78111 gold badge1313 silver badges4545 bronze badges
9
Answers
Question 1: "Is [finishing early to allow for testing] an acceptable request?"
Answer 1: It is completely reasonable because in Scrum, the Development Team is self-organizing:
No one (not even the Scrum Master) tells the Development Team how to turn Product Backlog into Increments of potentially releasable functionality - Scrum Guide
This means,...
9
Firstly, look at whether you can split your stories any more.
Secondly, why aren't the engineers on your team cooperating. The way your describing your system sounds like a you've set a minimum work in progress limit of one story per developer. Of course your cycle time is high (cycle time = wip / throughput after all). Instead cooperate on things to reduce ...
8
The It depends pretty much answers all of your questions because they really depend on the context.
My first advice is to change your questions by adding the why do I to the beginning. For example, "Why do I want to have one meeting per week?" Because I have to write a report once a week to my boss? Or, because I would like to know about the daily life of ...
8
David is absolutely right, there are very few instances whereby refusal to work can be considered acceptable, generally the accepted norms would be if to continue would compromise yourself and/or the organisation legally or as David has already said if to continue would constitute recklessness and present a risk to life etc. The developer’s behavior is ...
8
Disclaimer: I have never worked in a digital agency and I am aware that the role of Project Manager in Digital Agencies can be somewhat different to that commonly accepted in other I.T. operations whether in-house or software development suppliers. Furthermore I am not clear on the exact differences.
Despite my disclaimer above, and taking the question and ...
8
Keep in mind that different stories can have different users. If you are building you UI off of your own SDK, it isn't uncommon to have these two use stories:
As an SDK user, I would like to be able to grant permissions to a user
so that I can manage what different users can do.
and
As an interface user, I would like to be able to grant permissions ...
7
Unfortunately, you aren't doing Scrum. You simply apply certain practices, but not following the mindset. You are close when you are saying that "... every sprint gives us a version, a product which we can use but that we need to improve". However, sprints not necessarily produce versions and in Scrum we are aiming for feedback at the first place.
So, we do ...
7
This is a pretty big question that might create a lot of advice, but I'm sure there are also nuances that we will not get here. There are also multiple questions and challenges embedded into your question so I'm going to answer generally.
You are right that grouping by areas of expertise is considered a bad idea as now no one group of people actually has ...
7
TL;DR
TANSTAAFL. If you want to scale, you need to add more teams. However, if you add more teams, you have to manage the additional complexity and communications overhead that comes along with that.
Direct communication channels scale poorly. The formula is generally expressed as N(N-1)/2. If you don't have a project management model that addresses this ...
answered May 20 '13 at 13:00
7
There is a lot you can do that ensures that the code does what it's supposed to do, but aside from trusting the people developing it (including their reviewers) there is basically no way to make sure it does not do more.
But it comes down to that trust in any other job, too. At some level, you need to trust the people. If you cannot, get others that you ...
7
TL;DR
How to share developers between multiple agile projects?
You don't. Doing so is inherently non-agile.
This smacks of an X/Y problem, where X (the real problem) is likely to be an executive mandate to "do more with less" without prioritizing projects based on both business value and resource constraints. However, you or your organization may have ...
answered Nov 7 '16 at 17:28
6
I rather suspect that I would approach this as "tools & techniques to construct work packages". From my limited understanding, a "feature" is nothing more than a work package - a discrete deliverable with schedule & requirements.
I don't know of any software to assist in constructing and managing work packages, but I think that @CodeGnome's law ...
answered Nov 14 '12 at 13:18
Mark C. Wallace
7,91122 gold badges2424 silver badges4141 bronze badges
6
As far as I understand the question, and if you allow me some humor, you want to know if it is ok to change a pseudo-chaotic (non-)process into a highly bureaucratic PMBOKful one at once. Based on my experience the answer is no, for several reasons:
The team is not trained in such a heavy process and it will take a long time before they are efficient. Not ...
6
Sprints and Branches Are Separate Concepts
Can we say that a Sprint and a source code branch are almost the same things?
No, a Scrum Sprint and a Git branch are not at all the same things. While you can use an online Source Code Management (SCM) system like BitBucket or GitHub in the development process, there is no one-to-one mapping between the project ...
answered Dec 5 '14 at 16:41
6
Using a Behaviour Driven Development (BDD) or Acceptance Test Driven Development (ATDD) approach means that the code is self documenting. So introducing functionality beyond the original requirements would be obvious to anyone who paid attention to the code base.
What constitutes 'extra code' is a much more difficult question. It is quite possible that code ...
6
Welcome to PMSE!
From the Scrum Guide:
Individual Development Team members may have specialized skills and areas of focus, but accountability belongs to the Development Team as
a whole.
So, your goal should be to progressively move away from the notion of "dev owners of features". Also, it is good to set aside bandwidth for handling unforeseen ...
answered Apr 5 '19 at 8:55
Ashok Ramachandran
9,78111 gold badge1313 silver badges4545 bronze badges
6
Why should a developer want to work Agile?
Because a properly-implemented agile framework improves the pacing of a project and the sustainability of the developers' work efforts. It also increases collaboration between developers and stakeholders. If it doesn't do all of these things, then the team (or the organization) is probably Doing Agile Wrong™.
...
answered Aug 29 '19 at 20:40
5
I will argue that writing code is probably one of the least important parts of the project. In my view it is a means to an end, at the end of the day you are translating the requirements of a customer into a particular syntax that can be executed by a machine to deliver benefits to that customer.
"Requirements gathering, business and systems analysis" and "...
5
You cannot refuse to do work. You can offer up an objection, you can propose a few other alternatives and state your case, but you must always support the decision and the team and continue. As a PM, you cannot allow a team member to "refuse" to do work. The only time refusal is remotely acceptable is when something catastrophic is predicted: safety, life ...
5
There is a difference between estimates and planning values and I find most either ignore or confuse the two...probably the latter. Work effort is probabilistic and a proper estimate should reflect that and be provided as a range of possible results. For example, an estimate to build a wall might be six to 15 days, most likely nine. If you built that wall ...
5
Lead by example. You can't force people to do what they don't believe in, particularly in your role. But if you work the way you believe is right, and if you quietly show results, then you should eventually win people over to your side. Don't force anyone, simply work in the way you believe is right, mention your positive results, and if they are interested ...
5
TL;DR
I think the question of "requirements gathering" is based on a misunderstanding of the agile principles involved, and especially of how user stories are created and how the details of a story should be fleshed out into an implementation. Simply re-framing everyone's expectations properly may help a great deal.
While it may not be feasible to have 10 ...
answered Jan 30 '15 at 17:20
Only top voted, non community-wiki answers of a minimum length are eligible
Related Tags
development-process × 97software-development × 31
agile × 22
scrum × 21
team-management × 13
kanban × 8
project-management-style × 8
process × 8
jira × 7
methodology × 7
requirements × 6
product-management × 6
planning × 5
project-team × 5
estimation × 4
communication × 4
sprint × 4
time-management × 4
process-improvement × 4
process-engineering × 4
user-stories × 3
testing × 3
pm-software × 2
scheduling × 2
roles × 2