This is a weird test. You have a fixed time, fixed goal and fixed resources. Nothing there is flexible. There is no decisions to be made here. You are not a project manager, you are a project statistician. You can make the boards and graphs showing progress, but in the end, it's like a movie. It will play. It will either have a happy end or not. But none of ...


5

This scenario feels Waterfall because of the fixed scope of 8 epics and fixed schedule of 10/21/2021 so I wouldn’t say your feeling is off on that point. However, this is very much reality in many contexts therefore I can see some utility in this as an exercise in laying out a strategy or approach. With that said, you may start with working backwards from ...