Hot answers tagged

10

If you are the one responsible for reporting to the project management and they love Gantt Charts, there is maybe more damage not to do them then to do them even if you know they are not the correct way how to visualize the project. Ken Schwaber, the co-inventor of Scrum, describes similar situation he had during his experience in his book Agile Project ...


9

Not at all! The mindset (based on predictive process control, theory X) for which Gantt are invented as a tool are totally incompatible with the agile mindset (empiric process control, theory Y). Read this post by Jeff Sutherland (co-inventor Scrum) why Gantt chart were banned in the first Scrum sprints!


9

This would be possible in a project that has an overhead cost that is calculated by a fixed rate over the entire length of the project. One example I can think of is a building construction project. The job trailer, on-site temporary utilities, and on-site security fencing is a dollar-per-day rental cost. If you crash the schedule, then the total cost of ...


8

The WBS breaks down what you are building for the project into smaller, more manageable components. In most cases, the WBS should be things, not actions. The leaf level, the lowest decoposition of the WBS, is your work package. The work package, and the activities and resources--both human and materiel--are scheduled for deployment. You can include the ...


6

Check your task bar, top right there should be a pull-down menu you can select type of filtering. You will want to filter by "Date Range", you will then be prompted to enter start date and end date of the range. I don't know how to get to this through the menus.


6

Ummm ... Did you try out Google Docs' Gantt chart making feature? I recently used it for a project. This tutorial on Making a Gantt Chart with Google Docs might help you. Although there are better, quick and easy cloud products for making Gantt charts available on the Internet, I feel this feature of Google docs is much convenient to use as most of us are ...


6

Resource leveling will not move remaining work forward. The resource leveling command's sole function to the resolve resource overallations. If you want to move all remaining work out of the past, use the Tools > Tracking, Update Project, Reschedule uncompleted work to start after command. Do not keep changing the Project start date. Set your status date (...


6

The other way is to build trust. Your colleagues need to realize that the kind of planning they want to do is simply impossible and an outdated method of working in most cases. Gantt charts only work when the work to be done and the burn rate are very predictable. Neither of them is in software development. There is a better way of navigating these ...


5

In order to answer your question properly, I had to interview a lot of people, but I'm going to guess instead, because I cannot do it now. I think people love Gantt charts, because they give them a clear view on what is going to happen to them and when. The problem is that they take the chart as something written into stone. The inventor of the Gantt chart (...


5

Whilst David's answer is the right one in an ideal world, it is possible to achieve what you want by: Removing all the columns depicting start and end times (or moving the Gantt chart margin over them so they don't show), and Modifying the timescale appropriately- For example if you double-click on the timescale headings and remove all but one tier, then ...


5

Have you considered exporting the relevant data to Excel? If you display the Task Sheet (use the View ribbon) you can certainly save that view as PDF as well. Saving as PDF just prints the current view to a PDF printer. I would filter and show only the tasks of interest - instead of saving the entire list.


5

Yes there is value. Do you know the dependencies of all the tasks? Can you guarantee that you understand the critical path (your comment that "everything is on the critical path" strongly suggests that you don't fully understand the implications of critical path.) Are there alternate ways to organize the tasks that would result in a better delivery date? ...


5

An Agile concept that I've used to map somewhat nicely to a gantt-like chart is a Story Map. There are many different styles, you can research on the interwebz to find the one that seems to fit your project best. One of the common problems I've seen with agile development teams is that it's easy to get focused on this sprint and lose the overall sense of ...


4

A Gantt Chart is an outcome of "Develop Schedule" process, which gets a list of Activities as an income. Thus, I would suggest you to try one of those tools that allow you to maintain a list of Activities online (with multiple collaborators) and then automatically generate a Gantt Chart from them. Trac is one of the examples. But if you still need a pure ...


4

The value depends on how the Gantt is being used and maintained. The perception of limited value is usually due to a poor implementation, and lack of proper usage. The Gantt Chart is intended to be a visual representation of the project schedule. It gives you (and your team) a quick way to see how things are interrelated, how they are sequenced, ...


4

Gantt charts have value in the execution phase if the work breakdown structure tasks are being updated as things are completed, delayed, or adjusted. The effects of schedule slip and the identification of tasks that were over or under-estimated can be really obvious when shown in a Gantt view. If you were to ask this exact same question to someone in the ...


4

I second Trevor's description. What I would add is Critical Path analysis, but this is already done by most planning software Dependencies (inside or outside of the project), which require some time-buffering to mitigate possible slippage The Gantt is only a representation of the data behind it, based upon start and finish dates (baseline, planned, actual)...


4

Other possible solution would be to upload your MS Project file to google drive. Once there, try to open it and a popup will display asking you to use a couple of free tools: 1. Gantter for google drive 2. Project viewer for google drive Then, I guess you can share the file with your team. Another option would be to use Office 365 online. In that way, you ...


4

Part of the reasons we measure velocity and score stories weeks in advance (even though this is subject to change), is so we can project into the future. I think your boss is saying Gaant Chart, but what they really want is some kind of projection. Improve/split up the stories in your backlog ahead of time, score some stories, look at velocity, and see if ...


3

I agree with the comments you've gotten so far, the question is a little open-ended. But in the spirit of helping - I use the Gantt chart to give me a visual representation of things that haven't happened yet. I can look at it and see the flow of the project - when things are scheduled to be done, how tasks/deliverables relate to each other (dependencies), ...


3

The WBS is a time independent decomposition of the work requires to compete a project. After you assign owners and sequence the tasks, one output is the Gantt chart. The Gamnt is uaully at a much higher level.


3

Having recently compared many online Gantt solutions, I can also recommend Gantter.com as being one of the most polished and visually similar to MS Project. It still has bugs and the interface is cramped in a single browser window, but enables printing and optional tight integration with Google Drive. Possible security concerns if you install the optional ...


3

and Here is screen for Microsoft project 2010.


3

If you have a long-ish Gantt chart, it is common practice to report on the major milestones form the Gantt chart in a project presentation and leave the actual Gantt chart out all together. You might want to consider something like that, but since this is for a class, you might want to keep the milestones on a page and integral to the report and leave the ...


3

Gantt charts are not compatible with Scrum because in scrum dependencies of task are not fixed i.e it keeps on changing which in result can increase the complexity of gantt chart. So, I suggest not to use gantt charts in scrum - Avinav


3

Have you tried using the Date Selection provided in the Print Dialog? Date selection options are highlighted in blue color in the following screenshot: I tried it in MS Project 2007 and it worked fine. Full chart was taking 3 pages, when I used the date range then the chart got printed in 2 pages.


3

A Gantt chart is a scheduling and not a resource tool. It documents the planned order and inter-relationship of activities needed to develop project products, and from this you can identify a critical path, but not resource constraints. A program like Project will integrate resource calculations with scheduling calculations, but conceptually they are ...


3

As with everything in project management the answer is "it depends". The task list you mention would deliver roughly the same value as a Gantt, assuming your project isn't really complex. If your project is complex enough (however you choose to define complexity) a Gantt could be more useful just from the perspective that updating a Gantt will also spit out ...


3

Additional benefits of a one-man-band gantt chart: understanding interfaces: Even a simple project will have interfaces with other people, departments or processes. Are there any approvals, partial milestones, forms, inputs, meetings or reviews in addition to the start and end of the project? Something as silly as a meeting can take more than a week to ...


3

Although I am not familiar with Project Libre, my reading of that article is that the author refers to "Driving Milestones" to mean externally imposed milestones- the things that drive the project. Personally I don't see any practical difference between what he calls "Driving Milestones" and "Buoys", where Buoys are the "marker" milestones that surface from ...


Only top voted, non community-wiki answers of a minimum length are eligible