Hot answers tagged

1 vote

In a Gantt chart, how backwards arrows should be interpreted?

Additional Cues About Partial Overlap This answer seems to be basically correct, but I'd add that many Gantt chart applications use the color-coding on the bars to give you a visual cue of which part ...
Todd A. Jacobs's user avatar
  • 50.2k
1 vote
Accepted

In a Gantt chart, how backwards arrows should be interpreted?

ThCollignon, What you are showing is a finish-to-start with a lead. In MS Project it could look like the task dependency relationship shown for tasks "a" and task "b". However, a ...
john-project's user avatar