5
votes
Accepted
MS Project - How to print the right Gantt diagram from custom view?
If you have deleted all the bars with the exception of the Baseline Bars, you should not be seeing dependency lines nor start and finish dates. When you attempt to print, have you removed the ...
4
votes
How can I change the estimated dates value in MS Project 2010 without affecting plan dates?
Once you have established your schedule and you are satisfied with everything, you need to create a schedule baseline. The dates in the start and finish columns will populate the baseline start and ...
4
votes
Use elapsed days in german ms project
Insert the task Leveling Delay field into a table and read the unit abbreviation from there. Leveling Delay is always in elapsed days.
This will give you the answer in any language. German for ...
3
votes
Communicate a project easily without MS Project?
I agree with the previous comments and think that a kanban board could be a great solution for you. It is based on separating the board into the progress columns (the most simple approach - to do, ...
2
votes
MS-Project 2010 - How to add Task Name to the Quick Access ribbon?
Also F2 drops you into edit mode if the clicking twice doesn't work for you.
Previous releases had the Entry Bar enabled by default. You can display it in later releases through File, Options. However ...
2
votes
Accepted
Status Field and Microsoft Project
Don't worry MS-P is working fine. In the style of planning you describe, you may find that status is best used to help see how up to date your plan is and use Finish Variance as you already are, to ...
2
votes
Accepted
How can Critical Chain scheduling be undertaken with Microsoft Project 2010?
Sorry, Project does not use critical chain methodology - only critical path. There are add ins (ProChain for example) but not native to the product.
2
votes
How to Add an "Percent Tasks Complete" Column with Rollup to Summary Task (MS Project 2010)
Try using "% Complete" rather than "% Work Complete", Project will calculate % Complete automatically for "SafetyTest" if you have "SafetyTest1", "SafetyTest2" and "SafetyTest3" as subordinate tasks (...
2
votes
Accepted
After running visual report from Project 2010, why can't I modify the pivot table data?
I found that this can be accomplished using MDX(Multidimensional eXpressions) via the Excel PivotChartTools - Analyze tab. Under the Calculations section of the ribbon there is an OLAP Tools drop ...
2
votes
Task dates and project end date changes when adding a percent complete or changing resources
Assuming you are using Microsoft Project, take a look at your Calculation options in File > Options > Advanced. At the bottom of the Advanced page, there are options for how Project deals with the % ...
2
votes
Auto schedule problem with MS Project 2010
Do you have a must finish on constraint on the succeeding subtask and is that subtask fixed duration? If so, that would cause the subtask to start a day early to protect the must finish on constraint,...
2
votes
Accepted
Issue with task scheduling and ordering
1,2, & 3 should be auto-scheduled. 4 Should be manual-scheduled.
Drop all current predecessors for these. Then make 4 a predecessor of each of 1,2 & 3, using a S-F constraint.
You don't need ...
2
votes
Displaying a resource's tasks across multiple subprojects
This you can easily achieve using MS Excel, as Excel provides a good compatibility with Microsoft Project, so you can copy/paste all contents from Excel to MPP and vice versa.
Follow these steps:-
...
2
votes
Accepted
MS Project - One year is calculated wrong
Microsoft seems to have hard-coded 1 emo = 30 edays. There is no setting to achieve your expected date, which is based on the variable human interpretation of "month." For workarounds, I would ...
2
votes
MS Project, add hours directly in resource usage
I am not really sure I totally understood the problem; however, I am pretty sure that it's not a version or application problem.
I would give it a try and go to Project -> Change working Calendar and ...
1
vote
Sort Not Working in Microsoft Project Custom Report
I cannot reproduce the error. In Duration1 I have the following formula based upon your earlier post:
IIf([Baseline1 Finish]=ProjDateVAlue("NA")Or Not
IsDate([Finish]),0,IIf(ProjDateDiff([...
1
vote
MS Project VBA coding to include expiration date
I'm going to make an assumption that you don't have an agreement with the other party to have access to your IP. Generally anything developed by you on their time is theirs, but maybe these are macros ...
1
vote
In MS Project 2010, how to avoid a task of being split by non working time?
A couple of assumptions and feel free to adjust to your specific scenario.
If the sessions are 2.5 days each, they cannot start after 1:00 pm on Wed. Create a calendar with working time Monday ...
1
vote
MS Project: Multiple tasks for one employee
Within the tasks resource widget (double click on the task) you can set the % the resource is available for the task. Set it e.g. To 75% for development and 25% for testing.
But keep in mind that ...
1
vote
MS Project: Multiple tasks for one employee
Your tasks should be loaded as fixed units. Go to Resource Usage and spread the hours per task against the one resource manually. Don't let the tool level the tasks for your as it will split and ...
1
vote
Microsoft Project Task to Start and Finish on the Same Day?
If you can live with just the summary tasks, you can achieve what you are looking for with "buffer tasks" and two new base calendars. Before each of the main tasks, add a task with a one minute ...
1
vote
Auto schedule problem with MS Project 2010
If you need it to and nothing else works, and it's only this one subtask causing the issue set the predecessor to the task as (TaskID)FS+1d and that will add a lag.
ie. if the row is 14 then 13FS+1d
...
1
vote
Auto schedule problem with MS Project 2010
You lost me on the April then July dates - are they the same tasks? Check for Actual start dates on the tasks - display the Tracking table. No lead on the F to S link?
1
vote
Accepted
Task dates and project end date changes when adding a percent complete or changing resources
It is a bizarre quirk of MS-Project that setting a task to "Complete" by marking it as 100% Complete does not set the end-date to the current date. However I believe it does affect the task effort, ...
1
vote
MS Project Predecessor Path in Gantt Chart
Sadly not built-in to Project 2010. It is in Project 2013 through the "Task Path" feature. You can create your own Task Path Manually.
Add the Marked field (or a flag field) to the Gantt table. ...
1
vote
Accepted
Work statistics report for resources
With some tweaking you can get the chart from the Baseline Work Visual report. Open the master project you created using the pool and create the Baseline Work visual report.
Once the data is in ...
1
vote
Accepted
Finish variance in Hours
Go to Options in the File tab. Open Schedule. Third option group down, you can change how duration is entered. Choose hours.
1
vote
Accepted
Create resource dependencies in MS project 2010
Unless this is supported in Project Server, of which I have no experience, you cannot do this in MS-Project. It simply does not include the concept of resource dependencies within a task.
In any case,...
1
vote
How to reschedule activities after entering actuals in MS Project 2010
On the Project tab, under status date, there is an "update project" button. Is this what you mean?
1
vote
Accepted
MS-Project 2010 - How to add Task Name to the Quick Access ribbon?
Click on 'File' tab, select 'Options'.
The 'Project Options' dialogue window will open.
Select 'Display'. Check the 'Entry Bar' option.
Only top scored, non community-wiki answers of a minimum length are eligible
Related Tags
ms-project-2010 × 95ms-project × 88
scheduling × 9
ms-project-2013 × 5
reporting × 5
estimation × 4
planning × 3
resources × 3
ms-project-2016 × 3
dependencies × 3
schedule × 3
ms-project-2007 × 3
communication × 2
resource-planning × 2
pm-software × 2
tasks × 2
tracking × 2
deadline × 2
scrum × 1
agile × 1
time-management × 1
risk-management × 1
pmp × 1
tools × 1
backlog × 1