The “Actual Duration” of an in-progress summary task (including a project summary task) in MSP is NOT the same as – nor even closely related to – the elapsed work days from the start of the summary to the Status Date. Rather, the actual duration of the summary is the product of its duration and its %complete, where the latter is computed as a duration-...


0

I think the simple answer is that you have a mismatch between the calendar you are using to manually calculate duration and the standard calendar MSProject is using to calculate it. You need to build a calendar in MSProject to match what you are using offline. Or, just simply use MSProject's definition of the calendar and its duration outcome.