2 votes

Under what circumstances does resource levelling become necessary?

The act of leveling is to reschedule your work packages so that over utilized resources are reconciled. But it seems your interest is to identify over-utilized resources, which you can see by report. ...
David Espina's user avatar
  • 37.1k
1 vote

How we can calculate the free warranty time for a software application

You basically need to have a good estimate on the expected actual work required during the warranty period. This depends very much on what kind of fixes are covered by the warranty. If you have very ...
Hans-Martin Mosner's user avatar
1 vote

Is it possible to start with the amount of hours each person needs for each task and their availability, then drive the project schedule from that?

(Please excuse the German screen shots) I did it this way with your example data.... Solution 1 1. Sum Up Work Add an additional column to your table labelled Work and sum up the required hours: ...
John K. N.'s user avatar