15

They should absolutely be doing QA. In fact, in the ideal agile team there are no specific roles. Agile development is quite the opposite of the "throw it over the wall" mentality of development vs. QA. Clearly the problem is: if a feature is not Done, should people get off the story and do something else? And if QA is not irrelevant (in other words, it ...


13

TL;DR Part of any project management framework, but especially agile frameworks like Scrum, is the necessity of continuously managing stakeholder expectations. People want what they want when they want it, but a big part of project management is explaining to people what they can actually have within the various constraints impacting the project. As the ...


10

Great project management is not about hitting your targets 100% of the time. Much of our performance is probabilistic where many of the drivers of our results are out of control and very random. Missing your targets becomes a problem if it became a surprise for you as the PM and your customer. If you were monitoring properly, such as using critical path ...


9

TL;DR Targets and estimates are two different things. You're confusing the two, and setting your team up for failure. Targets vs. Estimates A target is something you assign to your team, such as "I want this set of tasks done in a month." Management targets are fine so far as they go, but they rarely provide a means to get there. For the actual ...


9

Should developers do QA? I guess it depends on what's more important to you: sticking to your job description to the letter (and interpreting being a developer as "I ain't do testing stuff, only write code"), or delivering working software as part of a team (which would imply that everyone is helping out each other as needed, even by doing ...


8

What's Wrong with Your Team's Processes When the deadline is tight and when there are not enough QA people, the Product Owner asks developers to join in with QA to meet the deadline. Your process problems are legion. Let me count at least some of the ways: Your Product Owner should never, ever be assigning work to the team. Your "developers" and "QA ...


7

Project managers manage variances. You will have both favorable and unfavorable ones. It is not a matter of "asking" but rather informing. Planning values that you choose, both cost and time, are single values that live in a probabilistic range of results. For example, your project has an estimate of finishing between three to nine months. You targeted ...


7

This is why I prefer a product oriented WBS. Except when the deliverable is a service, the WBS should be based on the product itself, broken down to its components, and then underneath add activities and tasks. Where you load resources is up to you but I typically load them at the lowest level product WBS. Below this, I could not care less what changes ...


7

Crashing is simply the concept of throwing more resources--be it money, tools and machinery, humans, etc--at a work package in an attempt to decrease its overall duration. The general idea is, if you planned 10 days with one person to do a task, then applying a second person will decrease the duration to five days. The issue is, this does not work that ...


7

TL;DR Like any project, things happen. I am looking for feedback on how to plan for the contingency in a scrum based project. [sic] This is an X/Y problem. In Scrum, you have estimates rather than guarantees, especially at the release-planning level. While you can always apply a fudge factor to any project management methodology, there is no cure for ...


6

The simple answer to "What does the PM do when the milestone passes" is: Re-schedule the project plan to take the delays into account then report on milestone changes back to the project sponsors and stakeholders. It is assumed that the PM would have been raising a risk to the project schedule in the risk log and talking to all relevant people in the run ...


4

The best way in every circumstance will boil down to understanding your client's perspective - including, but not limited to, the extent to which they value time as compared to cost and quality. It's always tempting for the project manager to paint a rosy picture and not inform the sponsor/client of a risk. That is usually the wrong thing to do because it ...


4

In my teams all developers would cross-check their developments/bugfixes: Review their code using a GIT pull request, Validate the behaviour by testing it in the browser, Validate the functional behaviour too - if it's illogical, it's the role of the peer to go to the functional expert/PM and check the development still makes sense. It's a great way to ...


4

To answer your question a generic sense - ALL estimates are wrong. Whether or not deviations are justifiable (or should be compensated) depends on the 'why' they were wrong. To address it in a more specific way - In the beginning of your question you said 'assume everything was done correctly' (i.e.: we were not at fault). Later you said 'we could not ...


4

The Problem [Are] there any cases...when wrong estimates can be justified? Estimates are not guarantees. They are "educated guesses" based on experience, historical data, and a set of assumptions. If you're being asked to "justify" your estimates, you are already playing the Blame Game™ and starting from a false premise. You can't win the Blame ...


4

Funny to read my name in the question. The documentation of this type of purposeful deviation could happen anywhere you normally document. For example, if an issue was identified and documented in the issue log, the recovery plan--a purposeful deviation from method or process--might be documented in the same log. It could be documented in a weekly report ...


4

I've been dealing a lot with a scope creep over the last 2 years. I created a list of things that is a must to keep in mind in order to minimize the negative impact on the project. At first - you should realize that scope creep will happen! You should: know the requirements; know the client's expectations; have balls to say "No". Saying "Yes" to placate ...


4

I'm a little bit worried about the way you phrased your question. From what I gather, you want some sort of formula or process to account for the risks, then use that formula to get the perfect estimate that will in turn protect you from those risks? Something like this doesn't exist. There are a few problems with that kind of logic (and with estimating in ...


3

Project Definition and agreement To be classified as a project, you need to have a defined scope, time plan (incl. milestones and deadline), resources and budget. If the client/customer have a deadline, it must be based upon a scope and a timeplan to start with. Before the contractor (your company) should agree on a deadline, the time plan should have been ...


3

Depending on what kind of planning you need. If you are looking for a project management tool for planning your progress, it is necessary to do so. You may try something like JIRA. If you are just looking for a way to share the progress with your team, you don't have to use any complex project management software. Instead, just share the files in Dropbox ...


3

Planning tools are always advantageous if used right, according to your specific needs. They improve your and your teams understanding on a plan and makes it easier to cope with deadlines. However, as it was already mentioned, a tool is just a tool. So the disadvantage would be that you still need to do the planning yourself, planning tools only enhance the ...


3

I don't know the specifics of agile, but having the same individual checking his/her own work is like having an inmate holding the keys to his cell. The incentives are different. The QA / QC person is incented to find as many defects as possible while the builder of product is incented to boast what a great job was done first time around. Now let's ...


3

TL;DR There isn't really any such thing as a "daily loss" in project management, since most projects are cost centers rather than profit centers. For example, you'd be hard-pressed to treat most projects as the sole topic of a profit-and-loss statement. However, you can certainly calculate the expenses of cost overruns due to a project exceeding its ...


3

A contingency plan is a set of actions you would deploy when certain predefined variables have been met. Prior to those variables coming true, the plan sits on the shelf. The specific structure of your contingency plan, or any plan, should be defined by you or your organization. It is great to reuse someone else's work but you need to hold the authority ...


3

I have formulated and defined the following view over many years and now use it quite successfully when I am at an interview seeking a role, and of course in real life when managing projects. Successful delivery (Waterfall method) comprises the following key elements to the Five-point Plan (MarvTM) Know your requirements in clear, accurate and unambiguous ...


3

Documentation is a Communication Aid Where is information such as deviations to be documented? There isn't a single answer for this, as it depends on what you're trying to document and the purpose of the communication. Deviations from a plan might even be documented in multiple places, and sometimes in different ways, depending on what you're trying to ...


3

One of the best solutions is to build in incentives and penalties tied to the schedule. You can have a T&M, Cost plus, or fixed price and still have a part of their fee at risk. If they finish early, provide a bonus. If late, some type of penalty. If you are working at a daily fixed rate, you are providing an incentive for the work to continue. ...


3

The short answer is that the project plan is more emergent than that - allow me to elaborate. In scrum I have a constantly evolving backlog. I work with the team to identify what work will be done in a sprint and we take that work to completion, but during that time, the product backlog could be changing with items being added, removed, or reprioritized. ...


3

Lets assume that the consultants are working in good faith and their estimates are correct. Now delays must be caused by the usual things: external task needs to be completed by someone else. extra requirements added during project missing external resources, api, servers, accounts etc Enumerate and record the actual reasons for the delays. "what could we ...


3

When possible, make it visible to the stakeholders why the release date is being pushed back. If it's in order to fix their own products, then they should naturally be less frustrated. It's even possible (if unlikely) that they could decide that the new development is a higher priority than the 'fire', thereby changing your priorities - it's good to give ...