The predecessors for Task C are: Task A Finish-to-Start Task B Finish-to-Finish If Task A is ID 1 and Task B is ID 2, the Predecessor field for Task C should be 1,2FF. Note that finish-to-start relationships are the default so the FS is not needed unless there is a lag (e.g. 1FS+2d would indicate start the task 2 days after task 1 finishes). Update Based ...