15 votes

Scrum and interruptions (urgent bugs, requests)

Does Scrum take into account interruptions? Scrum does not. The Scrum team does. Scrum teams are self-organized and plan their own work. If part of that work consists of fixing urgent bugs from ...
Bogdan's user avatar
  • 15k
13 votes
Accepted

For planning purposes, how many work hours per day should I expect of each staff member?

TL;DR In general, I recommend a "fudge factor" of 0.75 to baseline a new project, absent other data. This would mean 6 hours of project effort in an 8-hour day. I also recommend a more aggressive ...
Todd A. Jacobs's user avatar
  • 50.1k
10 votes

What to do when capacity is reduced in the middle of the Sprint? (e.g. Sick Leave)

How to Plan for Unplanned Absences People get sick, scope changes, and stuff happens. That's why velocity should always be measured as an average or a range, and primarily used as an upper bound on ...
Todd A. Jacobs's user avatar
  • 50.1k
7 votes

Scrum and interruptions (urgent bugs, requests)

TL;DR The Scrum framework certainly addresses capacity planning and scheduling, although it's not prescriptive about how the Scrum Team should manage the issues you describe. The implementation ...
Todd A. Jacobs's user avatar
  • 50.1k
6 votes
Accepted

Measuring team capacity for upcoming sprint on a Scrum Team

One other thing you could look at is past sprint variability. If, in the last 5 sprints (assuming nothing like a holiday is really skewing your numbers) you have an average of 35 points and your high ...
Daniel's user avatar
  • 16.9k
6 votes

Scrum and interruptions (urgent bugs, requests)

Scrum does address such problems through Inspection & Adaptation. If your team is wasting a % on repetitive work, it should come up at the end of the sprint as a source of waste. This source of ...
Tiago Cardoso's user avatar
  • 8,625
5 votes

Scrum and interruptions (urgent bugs, requests)

The first question is how frequent and impactful are these interruptions. The 2020 revision of the Scrum Guide refers to the Sprint as "the heartbeat of Scrum". If your team is highly ...
Thomas Owens's user avatar
  • 19k
5 votes

How can I measure team capacity in Kanban?

You have several options. None of them are exclusive to Kanban though. They all work perfectly fine with Scrum too. Story Points (start where you are!) Avg. Number of Cards Done / time unit (avg ...
RubberDuck's user avatar
  • 1,380
5 votes

What to do when capacity is reduced in the middle of the Sprint? (e.g. Sick Leave)

How can I identify the likelihood of the sprint being still completed using this new information? The team should handle this during the first stand-up, or a soon as they notice someone is sick, ...
Niels van Reijmersdal's user avatar
5 votes

Identifying and considering the important factors to calculate a persons Capacity for a Sprint?

I'm deducing that your team uses story points for an initial estimation then, at the planning meeting, breaks stories into tasks and estimates them at the hour level. First, some general suggestions:...
RubberDuck's user avatar
  • 1,380
4 votes

Identifying and considering the important factors to calculate a persons Capacity for a Sprint?

The Scrum Guide says this on the things to take account of when determining the commitments for the next sprint. The input to this meeting is the Product Backlog, the latest product Increment, ...
Nathan Cooper's user avatar
4 votes

Identifying and considering the important factors to calculate a persons Capacity for a Sprint?

TL;DR Estimate your team's capacity as an aggregate range based on historical performance, rather than as a sum of the ideal hours available to each individual. Furthermore, you should carefully ...
Todd A. Jacobs's user avatar
  • 50.1k
3 votes

How should we capture "non-implementation" work?

There are typically two ways to use velocity with sprints: Measure the team's capacity to do work - include all the work the team is doing in your calculations Measure the team's capacity to deliver ...
Barnaby Golden's user avatar
3 votes

How will team changes impact velocity of a Scrum project?

Velocity and Capacity 20% of the team left during the particular sprint. Does the velocity change? It is likely that your velocity will change because the team's capacity has changed, but a lot ...
Todd A. Jacobs's user avatar
  • 50.1k
2 votes

For planning purposes, how many work hours per day should I expect of each staff member?

80% is the figure I have always heard, although trying to find internet citations that support that figure is surprisingly difficult and, in fact, I wasn't able to find any! I have flip-flopped in ...
Marv Mills's user avatar
  • 4,424
2 votes

Different Scrum Teams Assisting Each Other - Good or Bad?

My answer and some associated comments (1, 2, 3, 4) appear to have sparked this question. The original question presented a very specific case - a Scrum team has met their Sprint Goals before the ...
Thomas Owens's user avatar
  • 19k
2 votes

How can I measure team capacity in Kanban?

TL;DR In Kanban, you generally aren't measuring "team capacity" because kanbans track queues, not people. The closest you are likely to come to a direct capacity measurement in Kanban in the WIP ...
Todd A. Jacobs's user avatar
  • 50.1k
2 votes

What to do when capacity is reduced in the middle of the Sprint? (e.g. Sick Leave)

When the whole team is planning their next sprint, slack should be built in for sick leave, meetings, fixing live incidents etc. Over the course of a year, assume most people will take around half of ...
user32613's user avatar
  • 2,436
2 votes

Scrum and interruptions (urgent bugs, requests)

If you really have as much as 30% on-demand work then your team might benefit from a Scrumban style approach. Prioritise your work on a board, with priority "buckets" taking the place of ...
nvogel's user avatar
  • 6,241
2 votes

How should we capture "non-implementation" work?

TL;DR This question is a close duplicate of What to do with work not on the board?. In my answer to that question, I articulate CodeGnome's Law of Transparency℠: "No invisible work, ever!" ...
Todd A. Jacobs's user avatar
  • 50.1k
1 vote

Team Velocity and Increasing Capacity

I assume the management is interested in increased capacity within the same team (i.e. delivering more with the same people). This can only happen if you have significant room for your team's flow ...
freedigit's user avatar
1 vote

How should we capture "non-implementation" work?

Why do you need to capture this type of work to predict velocity? Velocity is the measure of getting valuable work done. You can measure velocity in points, stories, or whatever else. Whatever your ...
Thomas Owens's user avatar
  • 19k
1 vote

Scrum and interruptions (urgent bugs, requests)

On top of what the previous commenter said that exactly The Scrum team does (plan time for bugfixing and tracking the regression), I would note that not all the bugs are blockers to deliver the ...
elisarea's user avatar
  • 303
1 vote

How will team changes impact velocity of a Scrum project?

You may be conflating two term here - velocity and capacity. Velocity is only measurable after the sprint and will most certainly be less for this sprint because you are short 2 people (by 20% left I'...
Daniel's user avatar
  • 16.9k
1 vote

For planning purposes, how many work hours per day should I expect of each staff member?

The best suggestion I would offer to anyone asking this is to ask each team member individually what they want to sign up for. Check in weekly to see if there are changes they want to make to this ...
Al Biglan's user avatar
  • 1,455
1 vote

Different Scrum Teams Assisting Each Other - Good or Bad?

There is a lot to unpack in there. The way I read the answer and associated comments, I interpret it as one team helping another gives the team the false impression that they can do more work than ...
Daniel's user avatar
  • 16.9k
1 vote

Identifying and considering the important factors to calculate a persons Capacity for a Sprint?

Try adopting the LEAN idea of 'waste' Get the team to record their hours against tasks, meetings, admin etc so that you can work out exactly how much time you are spending on 'non work' tasks each ...
Ewan's user avatar
  • 926
1 vote
Accepted

Can machine learning be used for capacity planning?

Although, this tool would sell like crazy, it won't be able to handle exceptions and variability (I believe it won't be able to handle vacation period, which is not too complicated for humans). ...
Zsolt's user avatar
  • 11.9k
1 vote

Who decides how much work should be included in each Sprint?

In my opinion, the following factors decides the stories to be included in each sprint. Product long term vision Product owner prioritizes the user stories in advance as per the requirement from ...
Jithin Antony's user avatar
1 vote

Who decides how much work should be included in each Sprint?

The key to not having this sort of problem is in determining the estimates right. One way to have reasonable estimates is to take estimates from each field expert and reason why he or she thinks so. ...
Ren's user avatar
  • 231