17

Following on Tiago's answer, the issue is not the methodology but how the methodology is being tailored on your projects. Based on my experience working on biodefence projects for US govt, as the complexity of a project increases so to does your need for upfront planning and thorough project oversight. Regardless of your use of waterfall or agile or ...


14

Well first thing is to remember that a retrospective, like a user story, is an invitation to a conversation. I wasn't there, so I can only take a guess as the meeting. It sounds like the retrospective may have ended up more focused on solution and not what the actual problem is. The scrum master (CSM is a certification, not a role) should start with some ...


13

If you are working alone, a software development methodology might be a bit expensive (time and additional research) for you, because the currently available methodologies were developed for teams which are cooperating and the need some ground rules in order to that. If you are working alone, you cannot really cooperate. My advise is cherry-pick those ...


12

Hard problem; I've seen that as well in the past. Analyze deeply what it is they're trying to improve in the whole. Then ask them hard questions, trying to get to the deeper problems before jumping to solutions. why you'd need Project Management meetings how the Scrum Meetings are not supporting that How creating a Gantt chart differs from creating a plan ...


10

Asking if there's a methodology that works fine for a large project sounds like asking if a map route can take someone from South America to Alaska. Is there any (methodology or map)? Yes. Will it do it (work or travel) by itself? Definitely, no. A methodology is a guideline. But, as the map, it's only suggestions of how to reach something or somewhere, ...


9

Classic X/Y Problem In the comments, the OP elaborated on his project environment. He said: [T]he major problem with our project is not that it is either big in KLOC/FP or "complex"...The problem is that the project is more like a "bowl of paperclips" more than a bunch of independent features - you can't touch any feature or issue without impacting most ...


8

"Self-organizing" does not mean uncontrolled You said: Given the team are self-organising and they are deciding to organise away from Scrum... I believe your development team is grossly exceeding their bounds on the pretext of "Self-organizing". To cite a small example, the stakeholders now have to wait for, say, nine months to see the first demo of ...


7

Waterfall is a software development life-cycle. It can be used in conjunction with project management frameworks and methodologies. Since the waterfall life-cycle depends on each phase to be completed in full to continue to the next phase, it is typically recommended only if there is a rigid set of well-defined requirements. If there is still a ...


7

Waterfall is a software development method because it is a process which provides structure, planning, and control for software development processes. It is not so easy to tell you if it's suitable to implement in your situation without more details. If you expect lots of changes in requirements that can comes during the time, and if you want to be able to ...


7

This is basically what Sprint Reviews in Scrum are about. At the beginning of each sprint, the team commits to deliver a working, deployable product increment including a certain number of backlog items. And in the end of each sprint, the team demonstrates to stakeholders the new features they have completed. In Scrum (and Agile approaches in general), the ...


7

Waterfall is not a methodology, it's a model. So, there are no strict restrictions and prescriptions like in well defined methodologies. Restrictions are more related with contract (not development model). If you have Fixed Price (or even Firm Fixed Price) contract (it is common practice in "waterfall" projects), it will be very hard to provide additional ...


7

My in-Sprint testplans always try to cover the area's defined in Brian Maricks described Agile testing quadrants. We look at each area at the beginning of the story and defined what effort we are going to put into it, but also if it is relavant for this story. Afterwards we create sub-tasks if needed. Agile: Focus is on test automation: https://less.works/...


7

Both Developers and Executives Broke the Agile Contract It was due for a release tomorrow but, as a result of a review by management, needs reworking. This will undoubtedly add a lot of time onto the estimate for release. You have a basic process failure if the first time your management team reviewed the product was shortly before release. In particular,...


7

I have been in a similar situation (in a retail bank), with consultants offering what they call 'enterprise Agile'. The result was waterfall and highly problematic. The consultancies are typically very good at lobbying support (especially with the executive). So it can be a challenge to call them out. I would recommend to your Agile coach that they do the ...


6

The definition of a project in agile terms is no different to that of a project in traditional terms. The difference is how the project is run and executed and the values behind the project. Common Both agile projects and traditional projects: have a start and end may be constrained by schedule, scope or budget should be for a single product; (lets not ...


6

Most of the answers here are excellent. I don't think you need high-quality written requirements, though. There are two types of things we build in software: Stuff that's new and differentiating Stuff that's similar to things we've done before and is well understood. For the first of these, it may be the case that it's new to the business, as well. Rather ...


5

Waterfall is used successfully on the largest projects in the world e.g. 500 people over 6 years at a cost of $21 billion. These are mostly infrastructure projects (bridges, tunnels and railways), aerospace and defense projects (airplanes and weapons systems) and energy projects (pipelines, drilling rigs) It is not the methodology that fails, but the ...


5

Arguably, waterfall is a software development methodology (at least wikipedia thinks so). However, a methodology is a defined set of tools, activities, tasks that offer guidance on how to provide a set of deliverables. In this respect (as a delivery mechanism), waterfall breaks down as a methodology because unless the amount of work that needs to be ...


5

You mention Definition of Done, and in Agile, the acceptance criteria and other user story content defines if work meets the user's needs, but often allows for shoddy workmanship. We all know we can cut corners to make things work in real-world environments. It's important to understand this has little, if anything, to do with the quality of the developer ...


5

Using an Agile approach while contrained by traditional contracts and customer attitudes can be very challenging. However, there are many aspects of Agile that should still be of value: Transparency Even when working with fixed scope and deadlines it is worth using the approach of incremental delivery. This helps to reduce risk and will build up trust ...


5

I think the crux of your question may actually lie in questions you posed in a comment, rather than in the question itself: Do you find it acceptable that release dates are not met? The answer is... it depends. It really depends on the situation; on the project itself. If it is a purely internal project that is a 'nice to have' or some such thing? Yes, ...


5

There is nothing agile about the consultant's approach and certainly not use of the Scrum framework. That is waterfall with some modern software development terms being misused. Allowing an internal team to learn through controlled experimentation is a good mentality; permitting a consultant to waste money for any length of time is ludicrous.


5

"Water-Scrum-Fall" is counter-productive Looks like "Water-Scrum-Fall" is a name coined by analyst firm Forrester Research to describe the reality of Agile found in many organizations. I would say they are referring to large and medium enterprises, because that is where they do most of their work. They could have called it "Hybrid", but I guess they wanted ...


5

The sprint timebox offers you iterations, which are a convenient pace-setting mechanism. For your question, we want to look at the idea of adding incremental development into the process. In incremental development, you complete fully-functioning and potentially shippable increments of the product regularly. You combine these together and you should have a ...


5

This is an unenviable position. I'm not sure there are any good/easy answers. Who is accountable in this scenario? Who approves the changes? Changes (last minute or not) have a financial impact on the company. What is the change control process? It isn't clear whether the 3 PM's who communicate with the clients have the authority to unilaterally ...


4

TL;DR You don't have a dependency on multiple stakeholders; you have a process failure at the interface between you and Agency #1. Shopping for alternative methodologies won't fix the process problem, but addressing it directly might. Re-Define Your Stakeholders From your description, you don't have any direct contact with the end user. While they may be ...


4

I take a different view to the other answers on here. The problem here is, clear cut, project management. The fundamental constraints appear to be: Long lead times for work definition Long lead times for work clarification Long lead times for budget approval Long lead times for work acceptance Long turn around time for defect reporting. Now scrum will ...


4

TL;DR "Agile" isn't a methodology; it's a set of principles espoused by the Agile Manifesto. SDLC is an ambiguous term that can refer to a specific, waterfall-like methodology or a generic lifecycle. Either way, frameworks like Scrum or Kanban are more usefully classified as project management methodologies rather than lifecycles. Frameworks Aren't ...


4

Although the Waterfall methodology was developed for software development, it has been adopted as one of the accepted project management methodologies and is used by lots of organizations. The way this has been adopted for the project management world is as clearly defined scope, pre-determined dedicated project team, modules and team dependencies ...


4

Measuring Velocity According to one source: Velocity is measured in the same units as feature estimates, whether this is story points, days, ideal days, or hours that the Scrum team delivers - all of which are considered acceptable. However, most sources don't really explain that velocity is based on the idea that you can extrapolate your ...