Task in WBS? This statement seems basically flawed to me. 8/80 principle relates to task scheduling. WBS is essentially a breakdown of total project into work packages.There is no tasks in the WBS. It is discussed in the Scope Knowledge Area. Tasks have no place in WBS. Tasks are defined in the schedule, which is in the schedule management knowledge area ...