Unanswered Questions

161 questions with no upvoted or accepted answers
4
votes
1answer
146 views

Determine to which task a resource is allocated on a particular day

Using a shared resource pool for several project plans (each plan is contained in a separate file), what is the simplest way of working out to which task a given resource is allocated on a particular ...
3
votes
2answers
214 views

How to determine project complete date?

As a project manager, I've already worked on a few tech projects with newly assembled teams every time. The team is usually 2-3 team members doing the actual work. It is hard to determine velocity. We ...
3
votes
0answers
83 views

Hiding a specific time period in Microsoft Project

Question Good morning, Is it possible on MS Project Pro 2019 to hide a period of time between two dates? Background Our construction projects are divided into 3 stages: (1) pre-construction, (2) ...
3
votes
1answer
119 views

Change task distribution with % completed

I'm using MS Project 2010. When assigning a task with duration say 5 days and work of say 10 hours. Then MSP distributes the occupation for that resource over the whole duration. e.g. Mon 2h | Tue ...
3
votes
0answers
130 views

How can I create a task for two developers to support testing?

I'm trying to create a timeline for server migration. Typically when it comes to testing our developers spend about 25% of their time supporting the testing. (Running batch processes, answering ...
3
votes
1answer
222 views

How can I show short tasks (less than 8 hours) in a JIRA Gantt chart?

I recently installed a few apps (like BigPicture) which help you see the order of work of each programmer. The problem is that when I link some tasks with estimates less than one work day, the Gantt ...
2
votes
0answers
77 views

PMBoK vs The Standard for Project Management

PMBoK is a collection of often used practices for project management. A project manager doesn't have to use all of them. An organization is supposed to adapt PMBoK for its needs. Why do we have The ...
2
votes
2answers
134 views

How do you map complex business data models & processes into a formal representation with validations?

I'm working at a small Brasil-based insurance company and one of the main pain points is implementing a new insurance product. I'm a relatively new internal project manager and really new to business ...
2
votes
1answer
23 views

How do you filter project tags in Azure Devops?

The list of projects we've got in Azure DevOps is rapidly growing and growing. It makes it difficult to focus on areas that need attention across the department though, and is taking a lot of Admin ...
2
votes
0answers
65 views

Auto-populate Lookup values from a custom field

I have written below code for custom field 'Product_task' to take values selected for field 'SFDC Product' as options. However this doesn't seem to work always. Please let me know your suggestions. ...
2
votes
0answers
35 views

How can I see 'next available' tasks in MS Project?

I'm used to creating project checklists in software such as OmniFocus, which shows me 'next available' tasks: those that are available now, aren't deferred, whose predecessors have been completed, etc....
2
votes
0answers
118 views

Ms project - Avoid task split up in minutes

I am trying to update my ms project plan with the following: - replan al 0% and partly completed tasks from the new status date. - Tasks can be split up - Plan based on priority and available time for ...
1
vote
3answers
89 views

portfolio optimization, with negative KPIs

In portfolio optimization, when having negative KPIs, what does it mean to select a subset of projects with contributions that result in a KPI end value to be less than 0? For example, if we have ...
1
vote
0answers
87 views

Fix for ProjectLibre incorrect critical path

I'm a big open source supporter, and want to switch from MS Project to ProjectLibre, however it does not display the critical path correctly for projects above a certain size. I'm wondering if anyone ...
1
vote
0answers
79 views

In MS project, sub project tasks are not showing up in sprint task board

I added multiple sub projects to my current master project. I don't see the sub project tasks in sprint task board though I assigned sprints to tasks and "show on board" is yes. The tasks ...

15 30 50 per page
1
2 3 4 5
11