Unanswered Questions

129 questions with no upvoted or accepted answers
3
votes
0answers
33 views

Hiding a specific time period in Microsoft Project

Question Good morning, Is it possible on MS Project Pro 2019 to hide a period of time between two dates? Background Our construction projects are divided into 3 stages: (1) pre-construction, (2) ...
3
votes
1answer
80 views

Change task distribution with % completed

I'm using MS Project 2010. When assigning a task with duration say 5 days and work of say 10 hours. Then MSP distributes the occupation for that resource over the whole duration. e.g. Mon 2h | Tue ...
3
votes
1answer
81 views

Determine to which task a resource is allocated on a particular day

Using a shared resource pool for several project plans (each plan is contained in a separate file), what is the simplest way of working out to which task a given resource is allocated on a particular ...
3
votes
3answers
741 views

Understanding Azure devops burndown

I do not understand why the burndown is looking like it is. Remaining work is higher than capacity - but in the details remaining work is lower than remaining capacity. Can anyone help?
3
votes
0answers
89 views

How can I create a task for two developers to support testing?

I'm trying to create a timeline for server migration. Typically when it comes to testing our developers spend about 25% of their time supporting the testing. (Running batch processes, answering ...
3
votes
0answers
123 views

Machine learning in Requirement change management

Good day! Looking for an example or a demo which describe complete process of requirement change management using similar historic change request using any machine learning technique or any data ...
3
votes
1answer
161 views

How can I show short tasks (less than 8 hours) in a JIRA Gantt chart?

I recently installed a few apps (like BigPicture) which help you see the order of work of each programmer. The problem is that when I link some tasks with estimates less than one work day, the Gantt ...
2
votes
0answers
33 views

Dynamically updating filters in a dashboard

The team I'm on has a couple dashboards for our projects tracking tickets that were completed. Our process is to create a filter for that weeks completed issues, and then create a new dashboard linked ...
2
votes
0answers
53 views

Auto-populate Lookup values from a custom field

I have written below code for custom field 'Product_task' to take values selected for field 'SFDC Product' as options. However this doesn't seem to work always. Please let me know your suggestions. ...
2
votes
0answers
31 views

How can I see 'next available' tasks in MS Project?

I'm used to creating project checklists in software such as OmniFocus, which shows me 'next available' tasks: those that are available now, aren't deferred, whose predecessors have been completed, etc....
2
votes
0answers
83 views

Ms project - Avoid task split up in minutes

I am trying to update my ms project plan with the following: - replan al 0% and partly completed tasks from the new status date. - Tasks can be split up - Plan based on priority and available time for ...
1
vote
0answers
21 views

Resource Assignments

I have 4 Work resources entered into the Resource sheet and each has standard rates. I assign the work resources to tasks, but one of the tasks continues to display $0.00. Then when I double-click the ...
1
vote
0answers
36 views

Project PWA - Project manager has access to the pool of all resource but should have access just to assigned on the project

The head of PMO allocates the resources for a project and adds resources for a project. One project manager can have several projects and the resource pool means all resources on all projects. A ...
1
vote
0answers
19 views

MS Project, Resource Availability, Task Usage work hours

I've been using other tools for awhile and have to jump back into MS Project. I started a high level plan with tasks and resources, however, I'm having trouble remembering the specifics around Task ...
1
vote
0answers
21 views

Approach for handling internal scheduling and global ticketing system in one JIRA instance

We have a following setup in my organization: Company-wide JIRA instance (over 3000 users I think) Organization JIRA instance (less than 200 hundred) with Tempo planner The reason we have an ...

15 30 50 per page
1
2 3 4 5
9