Unanswered Questions

132 questions with no upvoted or accepted answers
3
votes
1answer
69 views

Change task distribution with % completed

I'm using MS Project 2010. When assigning a task with duration say 5 days and work of say 10 hours. Then MSP distributes the occupation for that resource over the whole duration. e.g. Mon 2h | Tue ...
3
votes
0answers
63 views

Determine to which task a resource is allocated on a particular day

Using a shared resource pool for several project plans (each plan is contained in a separate file), what is the simplest way of working out to which task a given resource is allocated on a particular ...
3
votes
0answers
81 views

How can I create a task for two developers to support testing?

I'm trying to create a timeline for server migration. Typically when it comes to testing our developers spend about 25% of their time supporting the testing. (Running batch processes, answering ...
3
votes
1answer
145 views

How can I show short tasks (less than 8 hours) in a JIRA Gantt chart?

I recently installed a few apps (like BigPicture) which help you see the order of work of each programmer. The problem is that when I link some tasks with estimates less than one work day, the Gantt ...
3
votes
1answer
117 views

Machine learning in Requirement change management

Good day! Looking for an example or a demo which describe complete process of requirement change management using similar historic change request using any machine learning technique or any data ...
2
votes
0answers
17 views

Dynamically updating filters in a dashboard

The team I'm on has a couple dashboards for our projects tracking tickets that were completed. Our process is to create a filter for that weeks completed issues, and then create a new dashboard linked ...
2
votes
0answers
29 views

Jira Ticket best practices

I've been with two very different companies that both use JIRA Tickets to track work done. The first was corporate company with some high standards when it comes to defining Tickets in Jira, the ...
2
votes
2answers
88 views

In Jira, is there an issue type for creating an already completed task?

In Jira, I would like my employees to create an issue that already is complete and closed. The purpose of creating the issue is purely for auditing purposes as an official record that the incident ...
2
votes
0answers
52 views

Auto-populate Lookup values from a custom field

I have written below code for custom field 'Product_task' to take values selected for field 'SFDC Product' as options. However this doesn't seem to work always. Please let me know your suggestions. ...
2
votes
0answers
31 views

How can I see 'next available' tasks in MS Project?

I'm used to creating project checklists in software such as OmniFocus, which shows me 'next available' tasks: those that are available now, aren't deferred, whose predecessors have been completed, etc....
2
votes
0answers
67 views

Ms project - Avoid task split up in minutes

I am trying to update my ms project plan with the following: - replan al 0% and partly completed tasks from the new status date. - Tasks can be split up - Plan based on priority and available time for ...
1
vote
0answers
10 views

Task states besides “complete” and “incomplete” in TaskJuggler?

I am using TaskJuggler to manage a project. In my particular project, we are doing basic research, so some tasks are not guaranteed to be completed, due to large numbers of unknowns. I would like ...
1
vote
1answer
78 views

Do you tag user stories with iteration path, their tasks or both when using Azure DevOps?

We're using Azure devops, "agile settings". We write the user stories in different ways (combination "As a user..", "Do this", "Adjust SinglanR...", etc. We have a functional team (FA) that write ...
1
vote
0answers
15 views

Auto Scheduling in Microsoft Project Planning 2016 is not working as expected

I scheduled many tasks in the AUTO schedule, However, it is not taking/changing the dates once I link all the tasks. Due to that, I selected the start date manually which is resulting in a different ...
1
vote
0answers
47 views

How to manage Cross-teams Roadmaps and high level tasks

Do you have any recommendations to track Roadmaps when working with multiple teams and cross-teams projects? Right now we work with Jira and spreadsheets, so any useful templates or tips for combining ...

15 30 50 per page
1 2 3 4 5 9