Stack Exchange Network

Stack Exchange network consists of 175 Q&A communities including Stack Overflow, the largest, most trusted online community for developers to learn, share their knowledge, and build their careers.

Visit Stack Exchange

Unanswered Questions

98 questions with no upvoted or accepted answers
3
votes
1answer
36 views

MS Project - Link multiple columns to the Resource Sheet

I have (somehow) managed to create one column which successfully links to the Resource Sheet. When using the drop down, it brings up all of the names in the resource sheet, and allows you to choose ...
3
votes
1answer
2k views

How do you calculate the number of days between two tasks in Microsoft Project?

I've created an event planning project that explains all of the relevant tasks before, during, and after a given event in MS Project 2003. I would like to calculate the number of days between a given ...
3
votes
1answer
82 views

How can I show short tasks (less than 8 hours) in a JIRA Gantt chart?

I recently installed a few apps (like BigPicture) which help you see the order of work of each programmer. The problem is that when I link some tasks with estimates less than one work day, the Gantt ...
2
votes
1answer
40 views

How to divide a generic resource?

I am still new at using ms project Professional. My project has already assigned resources. For instance, let's take developers who together have a maximum effort of 200%, which means I have 2 ...
2
votes
1answer
48 views

Appropriate Structure to Manage Diverse IT Sustainment & Development Projects?

I am a consulting manager leading over 25 personnel to manage the infrastructure on a Navy Base. The team is currently segmented into Scrum Teams with: 5 SW Devs doing bug fixes and rewriting ...
2
votes
0answers
34 views

Change task distribution with % completed

I'm using MS Project 2010. When assigning a task with duration say 5 days and work of say 10 hours. Then MSP distributes the occupation for that resource over the whole duration. e.g. Mon 2h | Tue ...
2
votes
2answers
77 views

Project Management department organisation in large company - How to integrate skill silos?

Our company is facing a challenge regarding the project management organisation. We already have our own working group on this topic but I'd like to get some external opinions in. It's a very specific ...
2
votes
0answers
36 views

Ms project - Avoid task split up in minutes

I am trying to update my ms project plan with the following: - replan al 0% and partly completed tasks from the new status date. - Tasks can be split up - Plan based on priority and available time for ...
2
votes
0answers
36 views

Duration vs Work…Resource Overallocation Errors

I am fairly new to project so apologies up front...I have several tasks in my project plan which have a set duration; i.e. start and end dates/due dates, but the actual amount of time required for ...
2
votes
1answer
104 views

Looking for a way to remove an errant calendar from MS Project Professional 2013

I have a project file with a project calendar that shows up in the Change Working Time dialog box's For Calendar dropbox that is not being using in the project file. I've looked in the Calendar tab in ...
2
votes
1answer
3k views

Is there a way to use your customized fields in reports created in MS project 2013?

I have some customized fields that I've created. I really need to find a way to use them while I'm creating customized reports in MS project, but I just see the built-in fields when I want to create ...
1
vote
0answers
48 views

Project managment app that applies delays in one task into dates of other tasks

Let's say i have multiple tasks that are supposed to be taken care of one after another. Each has its own date of completion. task 1 - will be completed on 15 march (1 day) task 2 - will be completed ...
1
vote
0answers
23 views

How to update some Key information from another Project

I have created a Project in MS Project 2016. Of this data there are probably about 50 tasks which are of high importance. What I would like to do is create a project with the most important 50 tasks, ...
1
vote
0answers
143 views

Project Online - Enterprise Custom Field Not Calculating Formula Correctly?

I am new to MS Project (~1 week experience) and could use some help with an Enterprise Custom Field I'm trying to create. I'm using Project through Project Web App in Office 365 (I assume this is ...
1
vote
0answers
54 views

Asana and requirements management

I am looking for a way to include requirements management in Asana. Right now we have a very powerful integration with Instagantt, where projects and their scheduled tasks are in sync with Asana's ...

15 30 50 per page