Skip to main content
5 events
when toggle format what by license comment
Jul 1, 2015 at 18:06 comment added JulieS Correct, but the OP is using Project 2007.
Jun 30, 2015 at 16:34 comment added Adam Wuerl In Project 2013 Updated Project is in the Project tab of the ribbon, and still called Update Project.
Jan 10, 2014 at 21:55 comment added JulieS Ah, yes. Sorry - I read the question that he had remaining work in the past - not actual work in the future.
Jan 9, 2014 at 17:17 comment added Marv Mills Although this is a useful observation, it does not actually answer the OP's question, which is about moving Completed work into the past, not Uncompleted work into the future.
Jan 8, 2014 at 22:16 history answered JulieS CC BY-SA 3.0