Consider using a material resource with a cost of 13500. Then assign the material resource at 1/day in the task form.
In the Resource Names column it should look like this: Auger[1/day]
*Additionally, if there is a fixed cost plus a daily cost ($10,000 + $3,500/day) you can show this by entering $10,000 into the Cost Per Use column of the Resource Sheet and entering $3,500 into the Std. Rate column.