Mar 3, 2015 at 15:33 comment added JulieS Post back with whether you are using baselines and I'll step you through creating some custom formulas to test whether you are exceeding the baseline (Red), two weeks before the baseline finish (orange), etc.
Mar 3, 2015 at 15:31 comment added JulieS The finish date of a task is going to change as you track the task. For example: your original estimate was the task was going to take 10 days based upon two resources each working 80 hours. As the resources start working the task, they realize their initial estimates of 80 hours is too little. They've completed 40 hours (1 week) but need another 60 hour of work each. If you update the remaining work to 60 hours, Project will recalculate the new finish date. In order to compare - you need to set a baseline before tracking. Then I suggest comparing baseline finish to finish.