Timeline for In MS Project 2010, how to avoid a task of being split by non working time?
Current License: CC BY-SA 3.0
3 events
when toggle format | what | by | license | comment | |
---|---|---|---|---|---|
May 18, 2015 at 21:00 | comment | added | JulieS | If you have a Tuesday holiday and don't want the session to be split - you'll need to make that entire week non-working in the calendar for the "buffer" task. If you don't want the event split and it takes 2.5 days - then it has to start either Monday, Tuesday, or by 1:00 pm Wednesday. In the case of a Tuesday holiday, I'd make both Monday and Tuesday of those weeks non-working. The event needs to start on Wednesday in that circumstance. | |
May 18, 2015 at 17:11 | comment | added | Morts | Thanks for the suggestion. But case i have a Holiday on Tuesday, it looks like splitting will happen anyway. | |
May 18, 2015 at 14:40 | history | answered | JulieS | CC BY-SA 3.0 |