Timeline for In scrum should incomplete stories be re-estimated or does the original estimate get burned down when it's finally completed?
Current License: CC BY-SA 3.0
12 events
when toggle format | what | by | license | comment | |
---|---|---|---|---|---|
Jun 18, 2020 at 8:23 | history | edited | CommunityBot |
Commonmark migration
|
|
Feb 6, 2019 at 17:08 | answer | added | MacEncrypted | timeline score: 0 | |
Jun 7, 2018 at 22:14 | comment | added | Todd A. Jacobs♦ | "All incomplete Product Backlog Items are re-estimated and put back on the Product Backlog. The work done on them depreciates quickly and must be frequently re-estimated." scrumguides.org/scrum-guide.html#events-sprint | |
Aug 6, 2015 at 12:05 | history | tweeted | twitter.com/#!/StackProjects/status/629261945363918848 | ||
Aug 5, 2015 at 23:38 | answer | added | WBW | timeline score: 4 | |
Aug 5, 2015 at 8:50 | history | edited | Willl | CC BY-SA 3.0 |
added 396 characters in body
|
Aug 4, 2015 at 19:44 | vote | accept | Willl | ||
Aug 4, 2015 at 15:39 | answer | added | Todd A. Jacobs♦ | timeline score: 14 | |
Aug 3, 2015 at 11:51 | answer | added | Barnaby Golden | timeline score: 3 | |
Aug 3, 2015 at 11:26 | answer | added | Thomas Owens♦ | timeline score: 11 | |
Aug 3, 2015 at 11:21 | answer | added | Nikhil Gupta | timeline score: 1 | |
Aug 3, 2015 at 9:39 | history | asked | Willl | CC BY-SA 3.0 |