Timeline for How can I make task start date and finish date dependent upon the start & finish dates of one predecessor?
Current License: CC BY-SA 3.0
3 events
when toggle format | what | by | license | comment | |
---|---|---|---|---|---|
Nov 25, 2015 at 20:53 | comment | added | Scott C Wilson | Another spin - two milestone tasks (begin scaffolding and end scaffolding) which are SS and FF linked (respectively) to the scaffolding task, which is 20 days long. Then Brickwork linked appropriately. | |
Oct 21, 2015 at 11:21 | comment | added | AndrewD | Thanks Richard. That'd work, although it's a little clumsy. I'm surprised MSP can't cope with this set of dependencies. It must crop up a lot.....I feel a suggestion to MS coming on........Thx again | |
Oct 20, 2015 at 15:26 | history | answered | Richard | CC BY-SA 3.0 |