Nov 25, 2015 at 20:53 comment added Scott C Wilson Another spin - two milestone tasks (begin scaffolding and end scaffolding) which are SS and FF linked (respectively) to the scaffolding task, which is 20 days long. Then Brickwork linked appropriately.
Oct 21, 2015 at 11:21 comment added AndrewD Thanks Richard. That'd work, although it's a little clumsy. I'm surprised MSP can't cope with this set of dependencies. It must crop up a lot.....I feel a suggestion to MS coming on........Thx again
Oct 20, 2015 at 15:26 history answered Richard CC BY-SA 3.0