Timeline for Is it possible to prescribe PM time spent on key activities during a working day?
Current License: CC BY-SA 3.0
3 events
when toggle format | what | by | license | comment | |
---|---|---|---|---|---|
Mar 18, 2016 at 14:17 | history | edited | Alexander Averchenko | CC BY-SA 3.0 |
added 316 characters in body
|
Mar 18, 2016 at 14:08 | comment | added | Marv Mills | We should not forget the typical mid-project slump in requirements on PM time: Once everything is planned and underway, often there is reduced need for the PM as things run in an organised way. Then towards the end of projects there are again greater demands on a PM's time. This is not universal, and if a lot of risk and issue management is required then the PM needs to maintain their level of engagement, but it is the norm in my experience. | |
Mar 18, 2016 at 13:42 | history | answered | Alexander Averchenko | CC BY-SA 3.0 |