Timeline for Which Predecessors/Successor and constraint should I be using?
Current License: CC BY-SA 3.0
6 events
when toggle format | what | by | license | comment | |
---|---|---|---|---|---|
Jun 24, 2017 at 5:23 | history | bumped | CommunityBot | This question has answers that may be good or bad; the system has marked it active so that they can be reviewed. | |
May 25, 2017 at 4:22 | answer | added | Francisco Alcalá | timeline score: 1 | |
May 4, 2017 at 19:20 | comment | added | Tom Boyle | Also, get rid of all manual tasks; use a SNET constraint instead. Why is 3117 only 1hr instead of 1 day. Too many issues going on here to comment further. | |
May 4, 2017 at 19:02 | comment | added | Rachel Hettinger | Format the date columns so that time is also displayed. The task might not be starting at the beginning of the day. Also look at your constraint date. | |
May 4, 2017 at 18:49 | review | First posts | |||
May 4, 2017 at 20:38 | |||||
May 4, 2017 at 18:44 | history | asked | Michael A | CC BY-SA 3.0 |