I am totally new to Agile methodology and learning it. I have seen lots of tutorials and videoesvideos and they've all been very helpful. SoHowever, I have one unanswered question from my existing study. The situation is like:
In the beginning, there were a total of 100 story points. As part of Sprint 1, 10 arewere completed this. 90 points arewere still remaining but 10 additional points arewere added.This This makes, again, 100 story points in total.
In sprint 2, 20 story points were completed but no further additional in any of the sprintsnone were added, so total points becomebecame 80.
Again inIn Sprint 3, 15 story points arewere completed and this. Total story points come down to 65 points. and theThe cycle goes on. By the burndown chart, we can estimate some values like:-
Team's average velocity is 15.
In 8 sprints total, 120 story points will be covered.
To complete the work it will take around 7 sprints.
Unanswered question
- Product Backlog changing rate (My answer is 65 but I am not sure)
If someone can answer this and explain the way to calculate that, it will be very helpful.