Skip to main content
4 events
when toggle format what by license comment
May 13, 2018 at 19:46 comment added RibaldEddie I think you’re getting it. Don’t justify the cost of the entire project before starting. Instead, justify enough cost to run the initial stages for a few weeks and then see what is delivered. If it has value, keep going. If not, change direction and deliver something else. Keep iterating, and you’ll hit on something valuable a lot sooner and for less money than if you tried to hit a target a year away.
May 11, 2018 at 19:47 comment added Barnaby Golden It's a classic dilemma. If you want give the CEO gap and cost analysis on day 1 then you will need to nail down requirements and almost eliminate technical/project risks. That is the opposite of agile, which says nailing things down is pointless, much better to accept that change will happen and plan accordingly.
May 11, 2018 at 16:32 comment added Sarov I'm aware there are ways to provide the metrics, but the question posed to me was how to provide, at the beginning of the project, gap/cost analyses in order for the CIO to justify the project to the CEO. Am I correct in interpreting your Answer as "Don't; just fail fast and you won't need to justify at the beginning."?
May 11, 2018 at 15:42 history answered Barnaby Golden CC BY-SA 4.0