Timeline for What is the term for actual delivery time will be varied by 4 times from estimation?
Current License: CC BY-SA 4.0
4 events
when toggle format | what | by | license | comment | |
---|---|---|---|---|---|
Jul 10, 2018 at 17:14 | comment | added | Ashok Ramachandran | Yes. As you can see in the Wikipedia article, "The original conceptual basis of the Cone of Uncertainty was developed for engineering and construction in the chemical industry". However, in the software industry, because of technology uncertainty and scope creep, the range tends to be wider. | |
Jul 10, 2018 at 17:10 | comment | added | Ooker | does this apply to any industry? | |
Jul 10, 2018 at 17:10 | vote | accept | Ooker | ||
Jul 12, 2018 at 16:17 | |||||
Jul 10, 2018 at 17:10 | history | answered | Ashok Ramachandran | CC BY-SA 4.0 |