Feb 18, 2020 at 20:55 comment added nvogel During Sprint Planning the team need to decide how much work they can complete during the sprint. If you have to put a number on it then just reduce the ideal capacity (measured velocity in points) by the appropriate percentage of person-days PTO. In the end the team's assessment of what backlog items they can accomplish in the time available is more important than what number they put on it.
Feb 18, 2020 at 15:58 comment added Mark Saluta So, if I ask for the team's availability during the sprint, and John indicates that he has PTO Thursday and Friday at the end of the sprint, and I know he is going to be out for a total of 16 hours. How does this information impact the total capacity if not calculating based on hours?