Timeline for How can I get MS Project to display calendar days for duration rather than working days?
Current License: CC BY-SA 4.0
3 events
when toggle format | what | by | license | comment | |
---|---|---|---|---|---|
Aug 30 at 17:39 | comment | added | Kenny Arnold |
@ToddA.Jacobs Just know that edays assumes a 24 hour working day, rather than a standard 8 hour work day.
|
|
Aug 29 at 20:34 | comment | added | Todd A. Jacobs♦ |
While I appreciate your answer, and it may help someone else who has a calendar-based or resource-based scheduling issue, my problem was addressed by using edays ("elapsed days") rather than calendar- or effort-driven scheduling. Kudos on the easy to follow answer with clear images, though!
|
|
Aug 29 at 17:43 | history | answered | Kenny Arnold | CC BY-SA 4.0 |