Jul 1, 2013 at 1:27 | comment | added | Jacques Chester | Roberto -- imagine that your project is a machine. In one end goes money and time. Out the other end comes a bunch of outputs. The WBS is a breakdown of that output. It's not a blueprint or description of how the machine works: that's where planning comes in. | |
Jun 24, 2013 at 11:09 | comment | added | Stephan | The lowest level in your WBS is the work package; each Work package results into an output that is either a delverable for your project or an intermediate deliverable that is needed for something bigger. Work Packages are translated into your schedule (or task list) into the required tasks. | |
Jun 24, 2013 at 8:40 | comment | added | Radolino | I am actually missing the connecting link between the WBS and the task list. | |
Jun 23, 2013 at 23:43 | history | answered | Jacques Chester | CC BY-SA 3.0 |