Jul 1, 2013 at 1:27 comment added Jacques Chester Roberto -- imagine that your project is a machine. In one end goes money and time. Out the other end comes a bunch of outputs. The WBS is a breakdown of that output. It's not a blueprint or description of how the machine works: that's where planning comes in.
Jun 24, 2013 at 11:09 comment added Stephan The lowest level in your WBS is the work package; each Work package results into an output that is either a delverable for your project or an intermediate deliverable that is needed for something bigger. Work Packages are translated into your schedule (or task list) into the required tasks.
Jun 24, 2013 at 8:40 comment added Radolino I am actually missing the connecting link between the WBS and the task list.