If you are trying to indicate upcoming starts, upcoming finishes, and lateness, then here is a formula to get you started:

IIf([Start]-[Current Date]>=5,"Green",IIf([Start]-[Current Date]>=0,"Yellow",IIf([% Complete]>0,"Blue","Red")))

IIf([Start]-[Current Date]>=5,"Green",IIf([Start]-[Current Date]>=0,"Yellow",IIf([% Complete]>0,"Blue","Red")))

Insert this formula into a custom text field, and it will display various outputs under the following conditions:

  1. "Green" if the current date is greater than or equal to 5 days ahead of the start date.
  2. "Yellow" if the current date is less than 5 days and greater than or equal to 0 days ahead of the start date.
  3. "Blue" if the current date is past the start date and the task % complete is greater than 0 (i.e. the task has started).
  4. "Red" if the current date is past the start date and the task % complete is 0 (i.e. the task has not started).

You can use similar logic to create another custom calculated field based on the finish date.

Good luck!

Tony Zink | Vice President, EPMA | http://www.epmainc.com | Blog: http://www.epmablog.com

If you are trying to indicate upcoming starts, upcoming finishes, and lateness, then here is a formula to get you started:

IIf([Start]-[Current Date]>=5,"Green",IIf([Start]-[Current Date]>=0,"Yellow",IIf([% Complete]>0,"Blue","Red")))

Insert this formula into a custom text field, and it will display various outputs under the following conditions:

  1. "Green" if the current date is greater than or equal to 5 days ahead of the start date.
  2. "Yellow" if the current date is less than 5 days and greater than or equal to 0 days ahead of the start date.
  3. "Blue" if the current date is past the start date and the task % complete is greater than 0 (i.e. the task has started).
  4. "Red" if the current date is past the start date and the task % complete is 0 (i.e. the task has not started).

You can use similar logic to create another custom calculated field based on the finish date.

Good luck!

Tony Zink | Vice President, EPMA | http://www.epmainc.com | Blog: http://www.epmablog.com

If you are trying to indicate upcoming starts, upcoming finishes, and lateness, then here is a formula to get you started:

IIf([Start]-[Current Date]>=5,"Green",IIf([Start]-[Current Date]>=0,"Yellow",IIf([% Complete]>0,"Blue","Red")))

Insert this formula into a custom text field, and it will display various outputs under the following conditions:

  1. "Green" if the current date is greater than or equal to 5 days ahead of the start date.
  2. "Yellow" if the current date is less than 5 days and greater than or equal to 0 days ahead of the start date.
  3. "Blue" if the current date is past the start date and the task % complete is greater than 0 (i.e. the task has started).
  4. "Red" if the current date is past the start date and the task % complete is 0 (i.e. the task has not started).

You can use similar logic to create another custom calculated field based on the finish date.

Source Link

If you are trying to indicate upcoming starts, upcoming finishes, and lateness, then here is a formula to get you started:

IIf([Start]-[Current Date]>=5,"Green",IIf([Start]-[Current Date]>=0,"Yellow",IIf([% Complete]>0,"Blue","Red")))

Insert this formula into a custom text field, and it will display various outputs under the following conditions:

  1. "Green" if the current date is greater than or equal to 5 days ahead of the start date.
  2. "Yellow" if the current date is less than 5 days and greater than or equal to 0 days ahead of the start date.
  3. "Blue" if the current date is past the start date and the task % complete is greater than 0 (i.e. the task has started).
  4. "Red" if the current date is past the start date and the task % complete is 0 (i.e. the task has not started).

You can use similar logic to create another custom calculated field based on the finish date.

Good luck!