1

I am currently managing a project that is midway through execution. Unfortunately, the project is behind schedule and over budget, which is affecting overall progress. Recently, the customer has requested a change in performance requirements.

This change introduces a significant scope adjustment, which could potentially lead to further delays and additional costs. I need to balance the customer’s request while ensuring that the project is delivered in a timely and cost-effective manner.

How should I approach this situation to manage the scope change, mitigate the impact on the budget and schedule, and ensure that the customer remains satisfied, all while protecting my company’s profitability?

2 Answers 2

2

This sounds like a typical "waterfall" project, rather than an agile one, given your description of the situation. There are two issues here:

  1. The project is already over budget and behind schedule;
  2. The customer has requested a change to a key element of the project.

To deal with the first of these, you may need to go back to your contractual arrangements with the customer to determine what you can and can't do to recover the time and / or money. Bear in mind, however, that throwing more resources at a project that is running late is unlikely to have a significant impact if the project was resourced at a reasonable level up front. I would re-estimate the project to deliver the original scope and let the customer decide whether to continue to fund it. It may no longer be viable or deliver the required payback if it is late or costs more than was expected. Only the customer can make that call.

The second issue requires that a project change request be raised, explaining the impact in time and cost to deliver the new requirement. This must be presented to your customer and again, the customer has to decide whether to accept the cost and time impact. Your contract should allow for project changes to be accommodated.

Your customer may have to resolve an internal conflict: whether to go with the original scope and get the project delivered as soon as possible, then do the change as a "phase 2" (if that is even a logical option), versus delivering the project including the expanded scope in even more time and at even higher cost. This may actually require you to create three estimates:

  1. To deliver the "original" scope, accepting that this may cost more and / or be later than your current plan, without delivering the expanded scope;
  2. To fix the project and expand it to include the new scope;
  3. To deliver the new scope as a stand-alone phase after the original phase has been delivered.

Just to emphasise: your approach should be determined with reference to your company's contract with the customer, and decisions should be made by the customer as they are the people who are funding the project, and who have to decide whether it remains viable. Good luck!

0

Define the Scope:

  • Document the requested changes, comparing them to the original design.
  • Get the customer to agree to the above definitions.

Why?

  • To make it clear that these are not tweaks, but serious changes that impact the delivery.
  • To clearly define the new scope.

Propose Solutions:

  • Prepare two (or more) proposals.
  • One option being to add the changes to the existing delivery.
  • Another option being to deliver the original and then a second phase with the changes.
  • Other possibilities include a mix of the two: Some high-profile but "quick" changes for immediate delivery, others for a later delivery.
  • Define the amount of extra work involved for each proposal.
  • Create timelines for each proposal.
  • Calculate the extra cost involved.

Now let the customer decide which options to choose.

You have now put the burden of delaying the project on the customer, and the customer also realizes that these changes are not free.

BTW, when you create the new timelines, make sure to adjust your scheduling guesstimates to account for the slowness of the teams, which was wrongly assumed in the first proposal.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.