You can use standard FS relations for predecessors, and set task constraint type 'As late as possible':
1 milestone - 2,3 2 Activity A - 4 3 Activity B - 4 4 Activity C
You should set 'as late as possible' constraint on tasks 2-4, and set task 1 to the required fixed date ('start no earlier than' constraint).