I need to plan some activities backwards from a fixed deadline. I am used SF dependencies for that, andbut there's a slight problem. Let's say I have the following simple plan:
1 Milestone
2 Activity A 2 hours 1SF
3 Activity B 9 hours 1SF
4 Activity C 1 hour 2SF;3SF
I expect Activity C to start before BOTH Activity A and B (i.e., 9 hours before Milestone), but it starts before Activity A, only 2 hours before Milestone.
Is there a way to force MS Project to respect both constraints?