MS Project - tracking Tracking schedule after setting baseline

Source Link

MS Project - tracking schedule after setting baseline

In MS Project after setting a baseline, how do you show that a task is now estimated to take less time than originally thought?

For example the original estimated duration was 10 days, this was set as the baseline, but we now know that the task will only take 5 days.