Timeline for MS Project 2013: Can I avoid MSP auto-changing my assignment units to less than 100%?
Current License: CC BY-SA 3.0
2 events
when toggle format | what | by | license | comment | |
---|---|---|---|---|---|
Feb 16, 2018 at 11:44 | comment | added | Dimitar Kunov | Thanks, Rachel, that is probably what happens. However, as I'm using fixed unit setting (and not fixed duration), for tasks where work units exceed 8 hours, the duration is extended, and I'd expect that for tasks shorter than, the duration should be dynamically set to less than 1 day (0,5;0,4;0,3, etc.) keeping the resource availability intact, but alas, seems like a build-in logic in Microsoft Project. | |
Feb 15, 2018 at 20:01 | history | answered | Rachel Hettinger | CC BY-SA 3.0 |