Stockholder Stakeholder pushing to add more story instories into the sprint

Sprint planning is done  . Sprint backlog is ready  . Sprint goal is set  . Now stakeholder wants to add one more story, even though nothere's not enough capacity is there to deliver it. 

Team agreed to take this story, if we can remove any other story from sprint backlog to accommodate the new one . But, but stakeholder not happy with the removing idea . He wants allrefuses to remove any story from the user stories along with a new one Sprint backlog. Tried to convince him

I already explained that sprintthe Sprint goal is set and it’s weirdnot advised to disturbing this . We can take this story inchange the next sprint but hegoal when Sprint is very reluctantalready in progress. What other option do I have How to handle this situation?

Stockholder pushing to add more story in the sprint

Sprint planning is done  . Sprint backlog is ready  . Sprint goal is set  . Now stakeholder wants to add one more story even though no enough capacity is there . Team agreed to take this story if we can remove any other story from sprint backlog to accommodate the new one . But stakeholder not happy with the removing idea . He wants all the user stories along with a new one . Tried to convince him that sprint goal is set and it’s weird to disturbing this . We can take this story in the next sprint but he is very reluctant. What other option do I have ?

Stakeholder pushing to add more stories into the sprint

Sprint planning is done. Sprint backlog is ready. Sprint goal is set. Now stakeholder wants to add one more story, even though there's not enough capacity to deliver it. 

Team agreed to take this story, if we can remove any other story from sprint backlog to accommodate the new one, but stakeholder refuses to remove any story from the Sprint backlog.

I already explained that the Sprint goal is set and it’s not advised to change the goal when Sprint is already in progress. How to handle this situation?

Source Link
shailesh
  • 331
  • 2
  • 9

Stockholder pushing to add more story in the sprint

Sprint planning is done . Sprint backlog is ready . Sprint goal is set . Now stakeholder wants to add one more story even though no enough capacity is there . Team agreed to take this story if we can remove any other story from sprint backlog to accommodate the new one . But stakeholder not happy with the removing idea . He wants all the user stories along with a new one . Tried to convince him that sprint goal is set and it’s weird to disturbing this . We can take this story in the next sprint but he is very reluctant. What other option do I have ?