0

On a sample Prince2 exam online, I found that it says what risk response type can be used to respond to a threat and an opportunity. And the answer given is Share.

According to the diagram here, there is no single risk response type for both threat and opportunity. What am I not understanding correctly?

enter image description here

1
  • Comments are not for extended discussion; this conversation has been moved to chat. Commented May 10, 2016 at 22:28

1 Answer 1

1

enter image description here

I found the following online that explain this nicely

Share is both a response for threats and opportunities. Share is very common in customer/supplier projects where both parties share the gain if the costs are less than the planned costs and share the loss, too, if the costs are exceeded.

Example: In the concert example, suppose you have a supplier that provides VIP toilet facilities and people are charged €1 for each service. There is a certain fixed cost that you must pay to provide this service and you agree with the supplier to share the profits if the revenue is above this fixed cost amount and share the losses if it is below this amount.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.