I am preparing for the CAPM exam and following Rita's book.
But I couldn't figure out whether or not the above would be considered a Project.
It is also written:
Of the thousands of students RMC has taught, very few came into our classes understanding that you must first take what you are given and organize the work into appropriate projects. The project planning process will produce schedules and budgets. Can you schedule "fix it" if you do not know what is wrong? Of course not, so there are at least two projects in the previous story.
Why would there would be two projects?