0

Where should employees be located in matrix organization: co-located with project manager or with head of their department?

2
  • 1
    Matrix Management (or Organisation) is not a prescriptive definition of some organisational structure, it is a term describing, essentially, a situation where a resource's line manager is different from the manager overseeing their day-to-day activities. As such there is no definitive answer to your question and it may be in danger of closure as an "opinion poll".
    – Marv Mills
    Commented May 2, 2015 at 16:49
  • If you cannot avoid a matrix, the next best thing is to locate employees as close to day-to-day work as possible i.e. with project managers.
    – ottodidakt
    Commented May 3, 2015 at 4:02

1 Answer 1

2

If you talk about matrix organisations, you have to differ between the different kind of matrix organisations (see answer to What are differences between Project Manager, Project Expeditor and Project Coordinator?).

One of the motivations of strong matrix organisations is to concentrate domain specific knowledge, e.g. functional safety or how to create software architectures. Therefore it is necessary to share the specialists among different projects, otherwise they won't be able to keep their knowledge due to the fact that is is demanded during the project for a specific / short time only. If the specialist are located in a project independent department:

  • Their knowledge could be provided to several projects
  • They could share knowledge among specialist of the same domain which are also located in their department
  • Further education could be organised in a common way
  • Similar organisational aspects (payment, working hours, etc.) are concentrated

If the demand for highly specialised employees is very high, they should be organised around their functional manager, e.g. when their influence on project success is very high and their temporal assignment is short.

But be aware of the fact that you need a "critical mass" of projects demanding the special capability. Otherwise you might run better using subcontractors.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.