User story that contains a design task that generategenerates other tasks

I have some user stories that have a litle task aboutlittle tasks on basic design with highest priority. This tasktasks will lead to a conversation about the basic design of the user story and will generate other tasks for the user story. So, how would you handle this? 

I have been told that the design should be done in the sprint for each user story but this would change the sprint backlog because it will generate new takstasks derived from the created design what is not good.

One option would be just to add a full iteration where just design (just the necesarynecessary not athe whole) is done and will generate takstasks for the next iteration. But I guess this is not the right way to do it.

Could you comment how you solve this?

User story that contains a design task that generate other tasks

I have some user stories that have a litle task about basic design with highest priority. This task will lead to a conversation about the basic design of the user story and will generate other tasks for the user story. So, how would you handle this? I have been told that the design should be done in the sprint for each user story but this would change the sprint backlog because it will generate new taks derived from the created design what is not good.

One option would be just to add a full iteration where just design (just the necesary not a whole) is done and will generate taks for the next iteration. But I guess this is not the right way to do it.

Could you comment how you solve this?

User story contains a design task that generates other tasks

I have some user stories that have little tasks on basic design with highest priority. This tasks will lead to a conversation about the basic design of the user story and will generate other tasks for the user story. So, how would you handle this? 

I have been told that the design should be done in the sprint for each user story but this would change the sprint backlog because it will generate new tasks derived from the created design what is not good.

One option would be just to add a full iteration where just design (just the necessary not the whole) is done and will generate tasks for the next iteration. But I guess this is not the right way to do it.

Could you comment how you solve this?

Post Migrated Here from stackoverflow.com (revisions)
Source Link
Notbad
  • 121
  • 4

User story that contains a design task that generate other tasks

I have some user stories that have a litle task about basic design with highest priority. This task will lead to a conversation about the basic design of the user story and will generate other tasks for the user story. So, how would you handle this? I have been told that the design should be done in the sprint for each user story but this would change the sprint backlog because it will generate new taks derived from the created design what is not good.

One option would be just to add a full iteration where just design (just the necesary not a whole) is done and will generate taks for the next iteration. But I guess this is not the right way to do it.

Could you comment how you solve this?