Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the event is usually shorter. According to the scrum guide it sounds like the meeting has two parts: What can be done this Sprint and how will the chosen work get done

If your product backlog refinement is done well and all dependencies, priorities and acceptance criteria is ironed out, then we should be able to easily take items from the backlog to the sprint.

In part one of the sprint planning we can set the sprint goal and select the relevant items for the sprint. Part two of the meeting the how is already discussed in backlog refinement.

Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the event is usually shorter.

I understand there is a maximum timebox but not a minimum, so is it possible to have a short sprint planning meeting?

Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the event is usually shorter. According to the scrum guide it sounds like the meeting has two parts: What can be done this Sprint and how will the chosen work get done

If your product backlog refinement is done well and all dependencies, priorities and acceptance criteria is ironed out, then we should be able to easily take items from the backlog.

In part one of the sprint planning we can set the sprint goal and select the relevant items for the sprint. Part two of the meeting the how is already discussed in backlog refinement.

Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the event is usually shorter.

I understand there is a maximum timebox but not a minimum, so is it possible to have a short sprint planning meeting?

Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the event is usually shorter. According to the scrum guide it sounds like the meeting has two parts: What can be done this Sprint and how will the chosen work get done

If your product backlog refinement is done well and all dependencies, priorities and acceptance criteria is ironed out, then we should be able to easily take items from the backlog to the sprint.

In part one of the sprint planning we can set the sprint goal and select the relevant items for the sprint. Part two of the meeting the how is already discussed in backlog refinement.

Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the event is usually shorter.

I understand there is a maximum timebox but not a minimum, so is it possible to have a short sprint planning meeting?

Source Link
Ruan
  • 784
  • 6
  • 12

Why is sprint planning so long if your backlog is ready and prioritized

Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the event is usually shorter. According to the scrum guide it sounds like the meeting has two parts: What can be done this Sprint and how will the chosen work get done

If your product backlog refinement is done well and all dependencies, priorities and acceptance criteria is ironed out, then we should be able to easily take items from the backlog.

In part one of the sprint planning we can set the sprint goal and select the relevant items for the sprint. Part two of the meeting the how is already discussed in backlog refinement.

Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the event is usually shorter.

I understand there is a maximum timebox but not a minimum, so is it possible to have a short sprint planning meeting?