asAs displayed in the Microsoft project 2010 screenshot below, why my fatherthe summary task (Create DS<Batch: file->file>) has 52hrs work whenwhereas the sum of 2 child tasktasks is just 12h?
any idea are appreciated!
update: I'm using Microsoft project 2010
solved
Solved: So, checkCheck to make sure that none of your summary tasks have resources assigned