1

Currently our team members report any impediments in the Daily Scrum Standup and the ScrumMaster takes ownership of them and gets them resolved. I would like to know whether we should track Impediments in the Agile PM tool just like User Stories and Defects/Bugs.

1 Answer 1

3

Who Owns Impediments

The Scrum Master should not be "taking ownership" of impediments. The role of the Scrum Master is to facilitate communications and referee the process; the whole Scrum team is responsible for addressing impediments.

Tracking Impediments as Sprint Backlog Items

With that said, impediments that can be solved with a hallway meeting or a phone conversation probably don't need to be tracked. However, if the impediment is significant enough to generate an in-sprint task, you should definitely create a user story and place it on the Sprint Backlog.

Note that in-sprint user stories shouldn't add story points to the sprint, since they should generally be dependent stories of some other Sprint/Product Backlog item. However, if an impediment outgrows its parent story, either in level-of-effort or scope, then it needs to be escalated to the Product Owner to see if:

  • the user story can be added to the Product Backlog for a future sprint;
  • the user story that triggered the impediment can be refactored or removed without compromising the current Sprint Goal; or
  • the current sprint can be terminated early, followed immediately by a Sprint Retrospective and a return to Sprint Planning.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.